Analisis Waktu dan Biaya Penyelesaian Proyek Transmisi 150 kV Dengan Pendekatan Critical Path Method dan Time Cost Trade Off

The construction of the 150 kV Transmission electricity infrastructure by PT PLN (Persero) is an assignment from the Government in order to support electricity growth in Indonesia. Several 150 kV Transmission projects experienced delays in project completion due to inaccurate timing and project comp...

Full description

Bibliographic Details
Main Authors: Muhamad Eriq Ashari, Haryo Dwito Armono
Format: Article
Language:English
Published: Lembaga Penelitian dan Pengabdian kepada Masyarakat 2023-08-01
Series:Rekayasa
Subjects:
Online Access:https://journal.trunojoyo.ac.id/rekayasa/article/view/20501
_version_ 1797633118367121408
author Muhamad Eriq Ashari
Haryo Dwito Armono
author_facet Muhamad Eriq Ashari
Haryo Dwito Armono
author_sort Muhamad Eriq Ashari
collection DOAJ
description The construction of the 150 kV Transmission electricity infrastructure by PT PLN (Persero) is an assignment from the Government in order to support electricity growth in Indonesia. Several 150 kV Transmission projects experienced delays in project completion due to inaccurate timing and project completion costs. The construction project of the 150 kV transmission involves engineering, procurement, construction, and commissioning activities, requiring careful calculations of time and costs while considering resources (Man, Material, Machine, and Method). The Critical Path Method (CPM) is used as the deterministic analysis approach for time analysis, while the Time Cost Trade-Off (TCTO) method is employed when there is a potential for project delays, acceleration, or cost overrun. The combination of the CPM and TCTO methods is suitable for project activities that are precisely known, while considering both parallel and serial work. Based on the research results, the 150 kV transmission project has 13 critical paths. The acceleration scheme that significantly impacts time and cost is the acceleration during the construction phase, and changes in all resource variables (Man, Material, Machine, and Method) affect both time and cost. However, a change in a single resource variable, namely Method, may impact time but not necessarily cost.
first_indexed 2024-03-11T11:49:31Z
format Article
id doaj.art-1dd6d99dc2004067b452bf91355c55fb
institution Directory Open Access Journal
issn 0216-9495
2502-5325
language English
last_indexed 2024-03-11T11:49:31Z
publishDate 2023-08-01
publisher Lembaga Penelitian dan Pengabdian kepada Masyarakat
record_format Article
series Rekayasa
spelling doaj.art-1dd6d99dc2004067b452bf91355c55fb2023-11-09T09:55:39ZengLembaga Penelitian dan Pengabdian kepada MasyarakatRekayasa0216-94952502-53252023-08-0116219520310.21107/rekayasa.v16i2.205017836Analisis Waktu dan Biaya Penyelesaian Proyek Transmisi 150 kV Dengan Pendekatan Critical Path Method dan Time Cost Trade OffMuhamad Eriq Ashari0Haryo Dwito Armono1Sekolah Interdisiplin Manajemen & Teknologi, Institut Teknologi Sepuluh NopemberSekolah Interdisiplin Manajemen & Teknologi, Institut Teknologi Sepuluh NopemberThe construction of the 150 kV Transmission electricity infrastructure by PT PLN (Persero) is an assignment from the Government in order to support electricity growth in Indonesia. Several 150 kV Transmission projects experienced delays in project completion due to inaccurate timing and project completion costs. The construction project of the 150 kV transmission involves engineering, procurement, construction, and commissioning activities, requiring careful calculations of time and costs while considering resources (Man, Material, Machine, and Method). The Critical Path Method (CPM) is used as the deterministic analysis approach for time analysis, while the Time Cost Trade-Off (TCTO) method is employed when there is a potential for project delays, acceleration, or cost overrun. The combination of the CPM and TCTO methods is suitable for project activities that are precisely known, while considering both parallel and serial work. Based on the research results, the 150 kV transmission project has 13 critical paths. The acceleration scheme that significantly impacts time and cost is the acceleration during the construction phase, and changes in all resource variables (Man, Material, Machine, and Method) affect both time and cost. However, a change in a single resource variable, namely Method, may impact time but not necessarily cost.https://journal.trunojoyo.ac.id/rekayasa/article/view/20501infrastructure, electricity, resources, critical path
spellingShingle Muhamad Eriq Ashari
Haryo Dwito Armono
Analisis Waktu dan Biaya Penyelesaian Proyek Transmisi 150 kV Dengan Pendekatan Critical Path Method dan Time Cost Trade Off
Rekayasa
infrastructure, electricity, resources, critical path
title Analisis Waktu dan Biaya Penyelesaian Proyek Transmisi 150 kV Dengan Pendekatan Critical Path Method dan Time Cost Trade Off
title_full Analisis Waktu dan Biaya Penyelesaian Proyek Transmisi 150 kV Dengan Pendekatan Critical Path Method dan Time Cost Trade Off
title_fullStr Analisis Waktu dan Biaya Penyelesaian Proyek Transmisi 150 kV Dengan Pendekatan Critical Path Method dan Time Cost Trade Off
title_full_unstemmed Analisis Waktu dan Biaya Penyelesaian Proyek Transmisi 150 kV Dengan Pendekatan Critical Path Method dan Time Cost Trade Off
title_short Analisis Waktu dan Biaya Penyelesaian Proyek Transmisi 150 kV Dengan Pendekatan Critical Path Method dan Time Cost Trade Off
title_sort analisis waktu dan biaya penyelesaian proyek transmisi 150 kv dengan pendekatan critical path method dan time cost trade off
topic infrastructure, electricity, resources, critical path
url https://journal.trunojoyo.ac.id/rekayasa/article/view/20501
work_keys_str_mv AT muhamaderiqashari analisiswaktudanbiayapenyelesaianproyektransmisi150kvdenganpendekatancriticalpathmethoddantimecosttradeoff
AT haryodwitoarmono analisiswaktudanbiayapenyelesaianproyektransmisi150kvdenganpendekatancriticalpathmethoddantimecosttradeoff