Collaborative BIM-Based Construction Coordination Progress Modeling Using Extended Collaborative Process Modeling (exCPM)
Agile project management pursues repetitive and continuous management through an empirical process control method considering the complexity of the project. This study aimed to propose a collaborative Building Information Modeling (BIM)-based work process, focusing on construction coordination tasks...
Main Authors: | , , |
---|---|
Format: | Article |
Language: | English |
Published: |
MDPI AG
2024-01-01
|
Series: | Buildings |
Subjects: | |
Online Access: | https://www.mdpi.com/2075-5309/14/2/358 |
_version_ | 1797298672199794688 |
---|---|
author | Jae-Hyung Shim Nam-Hyuk Ham Jae-Jun Kim |
author_facet | Jae-Hyung Shim Nam-Hyuk Ham Jae-Jun Kim |
author_sort | Jae-Hyung Shim |
collection | DOAJ |
description | Agile project management pursues repetitive and continuous management through an empirical process control method considering the complexity of the project. This study aimed to propose a collaborative Building Information Modeling (BIM)-based work process, focusing on construction coordination tasks among participants during the construction phase of a project. The theoretical framework chosen for this endeavor was the Scrum framework, selected after analyzing previous research to align with the specific characteristics of construction coordination. Using the Scrum framework as a foundation, the study employed the exCPM methodology to model the collaborative BIM-based construction coordination progress. To validate the model, it underwent a transformation into a Petri-Nets model through the marked graph building block (MGBB) along with established rules for model conversion. The converted model was then subjected to validation through reachability tree analysis. The findings of this study hold applicability to diverse collaboration processes that leverage BIM in the construction industry. |
first_indexed | 2024-03-07T22:39:24Z |
format | Article |
id | doaj.art-2694da5c03614b66bedade818fa11d87 |
institution | Directory Open Access Journal |
issn | 2075-5309 |
language | English |
last_indexed | 2024-03-07T22:39:24Z |
publishDate | 2024-01-01 |
publisher | MDPI AG |
record_format | Article |
series | Buildings |
spelling | doaj.art-2694da5c03614b66bedade818fa11d872024-02-23T15:10:00ZengMDPI AGBuildings2075-53092024-01-0114235810.3390/buildings14020358Collaborative BIM-Based Construction Coordination Progress Modeling Using Extended Collaborative Process Modeling (exCPM)Jae-Hyung Shim0Nam-Hyuk Ham1Jae-Jun Kim2Department of Architectural Engineering, Hanyang University, 222, Wangsimni-ro, Seongdong-gu, Seoul 04763, Republic of KoreaDepartment of Digital Architecture and Urban Engineering, Hanyang Cyber University, 220, Wangsimni-ro, Seongdong-gu, Seoul 04763, Republic of KoreaDepartment of Architectural Engineering, Hanyang University, 222, Wangsimni-ro, Seongdong-gu, Seoul 04763, Republic of KoreaAgile project management pursues repetitive and continuous management through an empirical process control method considering the complexity of the project. This study aimed to propose a collaborative Building Information Modeling (BIM)-based work process, focusing on construction coordination tasks among participants during the construction phase of a project. The theoretical framework chosen for this endeavor was the Scrum framework, selected after analyzing previous research to align with the specific characteristics of construction coordination. Using the Scrum framework as a foundation, the study employed the exCPM methodology to model the collaborative BIM-based construction coordination progress. To validate the model, it underwent a transformation into a Petri-Nets model through the marked graph building block (MGBB) along with established rules for model conversion. The converted model was then subjected to validation through reachability tree analysis. The findings of this study hold applicability to diverse collaboration processes that leverage BIM in the construction industry.https://www.mdpi.com/2075-5309/14/2/358Agile project managementScrum frameworkconstruction coordinationBIMexCPM |
spellingShingle | Jae-Hyung Shim Nam-Hyuk Ham Jae-Jun Kim Collaborative BIM-Based Construction Coordination Progress Modeling Using Extended Collaborative Process Modeling (exCPM) Buildings Agile project management Scrum framework construction coordination BIM exCPM |
title | Collaborative BIM-Based Construction Coordination Progress Modeling Using Extended Collaborative Process Modeling (exCPM) |
title_full | Collaborative BIM-Based Construction Coordination Progress Modeling Using Extended Collaborative Process Modeling (exCPM) |
title_fullStr | Collaborative BIM-Based Construction Coordination Progress Modeling Using Extended Collaborative Process Modeling (exCPM) |
title_full_unstemmed | Collaborative BIM-Based Construction Coordination Progress Modeling Using Extended Collaborative Process Modeling (exCPM) |
title_short | Collaborative BIM-Based Construction Coordination Progress Modeling Using Extended Collaborative Process Modeling (exCPM) |
title_sort | collaborative bim based construction coordination progress modeling using extended collaborative process modeling excpm |
topic | Agile project management Scrum framework construction coordination BIM exCPM |
url | https://www.mdpi.com/2075-5309/14/2/358 |
work_keys_str_mv | AT jaehyungshim collaborativebimbasedconstructioncoordinationprogressmodelingusingextendedcollaborativeprocessmodelingexcpm AT namhyukham collaborativebimbasedconstructioncoordinationprogressmodelingusingextendedcollaborativeprocessmodelingexcpm AT jaejunkim collaborativebimbasedconstructioncoordinationprogressmodelingusingextendedcollaborativeprocessmodelingexcpm |