A new model for the multi-mode resource-constrained project scheduling problem with discount cash flows

This paper presents a mathematical model for the multi-mode resource-constrained project scheduling problem with maximizing the net present value of project. The proposed model is inspired by MRCPSP-GPR. Firstly, we presented an exact model solving MRCPSP_GPR then we expanded the model to estimate o...

Full description

Bibliographic Details
Main Authors: Amine Keramaty, Majid Esmaelian, Masoud Rabieh
Format: Article
Language:fas
Published: Allameh Tabataba'i University Press 2015-12-01
Series:Muṭāli̒āt-i Mudīriyyat-i Ṣan̒atī
Subjects:
Online Access:https://jims.atu.ac.ir/article_1979_4b5ee85788cc3abdd57445972659a52d.pdf
_version_ 1797367668953579520
author Amine Keramaty
Majid Esmaelian
Masoud Rabieh
author_facet Amine Keramaty
Majid Esmaelian
Masoud Rabieh
author_sort Amine Keramaty
collection DOAJ
description This paper presents a mathematical model for the multi-mode resource-constrained project scheduling problem with maximizing the net present value of project. The proposed model is inspired by MRCPSP-GPR. Firstly, we presented an exact model solving MRCPSP_GPR then we expanded the model to estimate other cost-related options, penalty-related expenditure is a case in point. As a result of estimating different factors which impact on project scheduling such as reward and penalty of finishing the project, managers can efficiently make a better decision. For better adaptation with real conditions, we consider two payment methods in two objective functions. The adjusted schedule by proposed model and solving time was logical. Moreover, to verify the proposed model, a numerical example is solved in small size and the related computational results are illustrated in terms of schedules. In addition, computational results with a set of 36 test problems in various sizes are reported and the results analyzed.
first_indexed 2024-03-08T17:21:34Z
format Article
id doaj.art-330f63b260574ac59c378f07bae2361c
institution Directory Open Access Journal
issn 2251-8029
2476-602X
language fas
last_indexed 2024-03-08T17:21:34Z
publishDate 2015-12-01
publisher Allameh Tabataba'i University Press
record_format Article
series Muṭāli̒āt-i Mudīriyyat-i Ṣan̒atī
spelling doaj.art-330f63b260574ac59c378f07bae2361c2024-01-03T04:44:17ZfasAllameh Tabataba'i University PressMuṭāli̒āt-i Mudīriyyat-i Ṣan̒atī2251-80292476-602X2015-12-01133963901979A new model for the multi-mode resource-constrained project scheduling problem with discount cash flowsAmine Keramaty0Majid Esmaelian1Masoud Rabieh2کارشناسی ارشد مدیریت صنعتی دانشگاه اصفهاناستادیار گروه مدیریت دانشگاه اصفهاناستادیار گروه مدیریت صنعتی دانشگاه شهید بهشتیThis paper presents a mathematical model for the multi-mode resource-constrained project scheduling problem with maximizing the net present value of project. The proposed model is inspired by MRCPSP-GPR. Firstly, we presented an exact model solving MRCPSP_GPR then we expanded the model to estimate other cost-related options, penalty-related expenditure is a case in point. As a result of estimating different factors which impact on project scheduling such as reward and penalty of finishing the project, managers can efficiently make a better decision. For better adaptation with real conditions, we consider two payment methods in two objective functions. The adjusted schedule by proposed model and solving time was logical. Moreover, to verify the proposed model, a numerical example is solved in small size and the related computational results are illustrated in terms of schedules. In addition, computational results with a set of 36 test problems in various sizes are reported and the results analyzed.https://jims.atu.ac.ir/article_1979_4b5ee85788cc3abdd57445972659a52d.pdfrectangle packingmulti modepayment methodscosts of overtimenet present value
spellingShingle Amine Keramaty
Majid Esmaelian
Masoud Rabieh
A new model for the multi-mode resource-constrained project scheduling problem with discount cash flows
Muṭāli̒āt-i Mudīriyyat-i Ṣan̒atī
rectangle packing
multi mode
payment methods
costs of overtime
net present value
title A new model for the multi-mode resource-constrained project scheduling problem with discount cash flows
title_full A new model for the multi-mode resource-constrained project scheduling problem with discount cash flows
title_fullStr A new model for the multi-mode resource-constrained project scheduling problem with discount cash flows
title_full_unstemmed A new model for the multi-mode resource-constrained project scheduling problem with discount cash flows
title_short A new model for the multi-mode resource-constrained project scheduling problem with discount cash flows
title_sort new model for the multi mode resource constrained project scheduling problem with discount cash flows
topic rectangle packing
multi mode
payment methods
costs of overtime
net present value
url https://jims.atu.ac.ir/article_1979_4b5ee85788cc3abdd57445972659a52d.pdf
work_keys_str_mv AT aminekeramaty anewmodelforthemultimoderesourceconstrainedprojectschedulingproblemwithdiscountcashflows
AT majidesmaelian anewmodelforthemultimoderesourceconstrainedprojectschedulingproblemwithdiscountcashflows
AT masoudrabieh anewmodelforthemultimoderesourceconstrainedprojectschedulingproblemwithdiscountcashflows
AT aminekeramaty newmodelforthemultimoderesourceconstrainedprojectschedulingproblemwithdiscountcashflows
AT majidesmaelian newmodelforthemultimoderesourceconstrainedprojectschedulingproblemwithdiscountcashflows
AT masoudrabieh newmodelforthemultimoderesourceconstrainedprojectschedulingproblemwithdiscountcashflows