Assessment of the Cost and Time Impact of Variation Orders on Construction Projects in Sulaimani Governorate

Variation orders are an on-going phenomenon in construction and industry projects worldwide, particularly in the province of Sulaimani, where the project's damage from cost and schedule overrun because of variation orders. However, the effect on project costs and time overrun of variation order...

Full description

Bibliographic Details
Main Authors: Karukh Hassan Mohammad, Noori Sadiq Ali, Basira Majeed Najm
Format: Article
Language:English
Published: University of Baghdad 2021-02-01
Series:Journal of Engineering
Subjects:
Online Access:https://joe.uobaghdad.edu.iq/index.php/main/article/view/1297
_version_ 1827851835580350464
author Karukh Hassan Mohammad
Noori Sadiq Ali
Basira Majeed Najm
author_facet Karukh Hassan Mohammad
Noori Sadiq Ali
Basira Majeed Najm
author_sort Karukh Hassan Mohammad
collection DOAJ
description Variation orders are an on-going phenomenon in construction and industry projects worldwide, particularly in the province of Sulaimani, where the project's damage from cost and schedule overrun because of variation orders. However, the effect on project costs and time overrun of variation order has yet to be identified. This study evaluates the impact of variation orders on the cost and time off in the Sulaimani governorate. Two hundred twenty-eight projects from various construction sectors built between 2007-2012 were adopted to calculate the contract cost and schedule overruns due to variation orders. Data analysis was applied in the study were descriptive statistics. One-way ANOVA was also applied to determine whether the overrun of project cost and schedule significantly varied depending on project type, size, duration, location, and awarded years. The findings indicated that cost overruns are very common due to variation orders. 95.6% of the projects were studied being impacted, and overrun in project cost are also huge, with 16%. Time also overruns more common than cost overruns due to the variation orders. 98.7% of the projects were studied in Sulaimani were affected by time overrun with an average of 46.3% of initial duration observed. Findings also indicated that two out of five parameters measured in the analysis had a significant correlation with project cost overruns. Three out of five considered variables correlated with construction time overruns.
first_indexed 2024-03-12T10:39:27Z
format Article
id doaj.art-398804bca33847488ae322c5aa739762
institution Directory Open Access Journal
issn 1726-4073
2520-3339
language English
last_indexed 2024-03-12T10:39:27Z
publishDate 2021-02-01
publisher University of Baghdad
record_format Article
series Journal of Engineering
spelling doaj.art-398804bca33847488ae322c5aa7397622023-09-02T08:17:05ZengUniversity of BaghdadJournal of Engineering1726-40732520-33392021-02-0127210.31026/j.eng.2021.02.08Assessment of the Cost and Time Impact of Variation Orders on Construction Projects in Sulaimani GovernorateKarukh Hassan Mohammad0Noori Sadiq Ali1Basira Majeed Najm2College of Engineering-University of Sulaimani, Sulaimani, IraqCollege of Engineering- University of Cihan- Erbil - IraqCollege of Administration and Economic - Kurdistan Region- IraqVariation orders are an on-going phenomenon in construction and industry projects worldwide, particularly in the province of Sulaimani, where the project's damage from cost and schedule overrun because of variation orders. However, the effect on project costs and time overrun of variation order has yet to be identified. This study evaluates the impact of variation orders on the cost and time off in the Sulaimani governorate. Two hundred twenty-eight projects from various construction sectors built between 2007-2012 were adopted to calculate the contract cost and schedule overruns due to variation orders. Data analysis was applied in the study were descriptive statistics. One-way ANOVA was also applied to determine whether the overrun of project cost and schedule significantly varied depending on project type, size, duration, location, and awarded years. The findings indicated that cost overruns are very common due to variation orders. 95.6% of the projects were studied being impacted, and overrun in project cost are also huge, with 16%. Time also overruns more common than cost overruns due to the variation orders. 98.7% of the projects were studied in Sulaimani were affected by time overrun with an average of 46.3% of initial duration observed. Findings also indicated that two out of five parameters measured in the analysis had a significant correlation with project cost overruns. Three out of five considered variables correlated with construction time overruns.https://joe.uobaghdad.edu.iq/index.php/main/article/view/1297Construction projects, Cost overrun, Time overrun, Variation orders
spellingShingle Karukh Hassan Mohammad
Noori Sadiq Ali
Basira Majeed Najm
Assessment of the Cost and Time Impact of Variation Orders on Construction Projects in Sulaimani Governorate
Journal of Engineering
Construction projects, Cost overrun, Time overrun, Variation orders
title Assessment of the Cost and Time Impact of Variation Orders on Construction Projects in Sulaimani Governorate
title_full Assessment of the Cost and Time Impact of Variation Orders on Construction Projects in Sulaimani Governorate
title_fullStr Assessment of the Cost and Time Impact of Variation Orders on Construction Projects in Sulaimani Governorate
title_full_unstemmed Assessment of the Cost and Time Impact of Variation Orders on Construction Projects in Sulaimani Governorate
title_short Assessment of the Cost and Time Impact of Variation Orders on Construction Projects in Sulaimani Governorate
title_sort assessment of the cost and time impact of variation orders on construction projects in sulaimani governorate
topic Construction projects, Cost overrun, Time overrun, Variation orders
url https://joe.uobaghdad.edu.iq/index.php/main/article/view/1297
work_keys_str_mv AT karukhhassanmohammad assessmentofthecostandtimeimpactofvariationordersonconstructionprojectsinsulaimanigovernorate
AT noorisadiqali assessmentofthecostandtimeimpactofvariationordersonconstructionprojectsinsulaimanigovernorate
AT basiramajeednajm assessmentofthecostandtimeimpactofvariationordersonconstructionprojectsinsulaimanigovernorate