Model and application of renewable energy accommodation capacity calculation considering utilization level of inter-provincial tie-line
Abstract At present, the problem of abandoning wind and PV power in “Three North” region of China is particularly significant, and how to alleviate this problem has become the focus of universal attention. Calculation of renewable energy accommodation capacity is the basis to solve the problem of ab...
Main Authors: | , , |
---|---|
Format: | Article |
Language: | English |
Published: |
SpringerOpen
2019-01-01
|
Series: | Protection and Control of Modern Power Systems |
Subjects: | |
Online Access: | http://link.springer.com/article/10.1186/s41601-019-0115-7 |
_version_ | 1811214709260550144 |
---|---|
author | Guodong Li Gengyin Li Ming Zhou |
author_facet | Guodong Li Gengyin Li Ming Zhou |
author_sort | Guodong Li |
collection | DOAJ |
description | Abstract At present, the problem of abandoning wind and PV power in “Three North” region of China is particularly significant, and how to alleviate this problem has become the focus of universal attention. Calculation of renewable energy accommodation capacity is the basis to solve the problem of abandoning wind and PV power. Main problems of Chinese renewable energy accommodation is analyzed from power supply, power grid and load side aspects, and it focuses on the effect of inter-provincial tie-line to renewable energy accommodation capacity. At present, the inter-provincial tie-line utilization level is limited, which affected renewable energy accommodation to a certain extent. Based on the sequential production simulation model, a new kind of renewable energy accommodation capacity model is put forward considering the utilization level of inter-provincial tie-line. According to different system stability constraints and different electricity constraints of inter-provincial tie-line, 4 schemes are designed for comparative analysis, and the evaluation model is used to calculate renewable energy accommodation capacity of “Three North” region of China in 2020. Example analysis results verify validity of the model that releasing curve constraints, electricity constraints and stability constraints in turn can significantly enhance renewable energy accommodation capacity through effective use of inter-provincial tie-line transmission capacity. Research work in this paper can provide strong support for the planning and scheduling control of power grid. |
first_indexed | 2024-04-12T06:10:28Z |
format | Article |
id | doaj.art-41a2b7b46865442c968ebf90cd1f3206 |
institution | Directory Open Access Journal |
issn | 2367-2617 2367-0983 |
language | English |
last_indexed | 2024-04-12T06:10:28Z |
publishDate | 2019-01-01 |
publisher | SpringerOpen |
record_format | Article |
series | Protection and Control of Modern Power Systems |
spelling | doaj.art-41a2b7b46865442c968ebf90cd1f32062022-12-22T03:44:44ZengSpringerOpenProtection and Control of Modern Power Systems2367-26172367-09832019-01-014111210.1186/s41601-019-0115-7Model and application of renewable energy accommodation capacity calculation considering utilization level of inter-provincial tie-lineGuodong Li0Gengyin Li1Ming Zhou2Key Laboratory of Alternate Electrical Power System with Renewable Energy Sources, North China Electric Power UniversityKey Laboratory of Alternate Electrical Power System with Renewable Energy Sources, North China Electric Power UniversityKey Laboratory of Alternate Electrical Power System with Renewable Energy Sources, North China Electric Power UniversityAbstract At present, the problem of abandoning wind and PV power in “Three North” region of China is particularly significant, and how to alleviate this problem has become the focus of universal attention. Calculation of renewable energy accommodation capacity is the basis to solve the problem of abandoning wind and PV power. Main problems of Chinese renewable energy accommodation is analyzed from power supply, power grid and load side aspects, and it focuses on the effect of inter-provincial tie-line to renewable energy accommodation capacity. At present, the inter-provincial tie-line utilization level is limited, which affected renewable energy accommodation to a certain extent. Based on the sequential production simulation model, a new kind of renewable energy accommodation capacity model is put forward considering the utilization level of inter-provincial tie-line. According to different system stability constraints and different electricity constraints of inter-provincial tie-line, 4 schemes are designed for comparative analysis, and the evaluation model is used to calculate renewable energy accommodation capacity of “Three North” region of China in 2020. Example analysis results verify validity of the model that releasing curve constraints, electricity constraints and stability constraints in turn can significantly enhance renewable energy accommodation capacity through effective use of inter-provincial tie-line transmission capacity. Research work in this paper can provide strong support for the planning and scheduling control of power grid.http://link.springer.com/article/10.1186/s41601-019-0115-7Renewable energy accommodation capacitySequential production simulationInter-provincial tie-lineStability constraints |
spellingShingle | Guodong Li Gengyin Li Ming Zhou Model and application of renewable energy accommodation capacity calculation considering utilization level of inter-provincial tie-line Protection and Control of Modern Power Systems Renewable energy accommodation capacity Sequential production simulation Inter-provincial tie-line Stability constraints |
title | Model and application of renewable energy accommodation capacity calculation considering utilization level of inter-provincial tie-line |
title_full | Model and application of renewable energy accommodation capacity calculation considering utilization level of inter-provincial tie-line |
title_fullStr | Model and application of renewable energy accommodation capacity calculation considering utilization level of inter-provincial tie-line |
title_full_unstemmed | Model and application of renewable energy accommodation capacity calculation considering utilization level of inter-provincial tie-line |
title_short | Model and application of renewable energy accommodation capacity calculation considering utilization level of inter-provincial tie-line |
title_sort | model and application of renewable energy accommodation capacity calculation considering utilization level of inter provincial tie line |
topic | Renewable energy accommodation capacity Sequential production simulation Inter-provincial tie-line Stability constraints |
url | http://link.springer.com/article/10.1186/s41601-019-0115-7 |
work_keys_str_mv | AT guodongli modelandapplicationofrenewableenergyaccommodationcapacitycalculationconsideringutilizationlevelofinterprovincialtieline AT gengyinli modelandapplicationofrenewableenergyaccommodationcapacitycalculationconsideringutilizationlevelofinterprovincialtieline AT mingzhou modelandapplicationofrenewableenergyaccommodationcapacitycalculationconsideringutilizationlevelofinterprovincialtieline |