ELECTRICAL LOAD RELIABILITY ASSESSMENT USING ANALYTICAL METHOD, CASE STUDY: FUPRE 1 X 2.5MVA INJECTION SUBSTATION
This research work presents the reliability assessment of electrical load distribution system in Federal University of Petroleum Resources, Effurun (FUPRE), Warri using the Analytical method and ETAP software as the simulation tool to run the reliability assessment of the System. The analytical ana...
Main Authors: | , |
---|---|
Format: | Article |
Language: | English |
Published: |
Alma Mater Publishing House "Vasile Alecsandri" University of Bacau
2020-07-01
|
Series: | Journal of Engineering Studies and Research |
Subjects: | |
Online Access: | https://jesr.ub.ro/1/article/view/205 |
_version_ | 1797202252320997376 |
---|---|
author | AMAKIRI OKILO FRIDAY OSHEVIRE PATRICK |
author_facet | AMAKIRI OKILO FRIDAY OSHEVIRE PATRICK |
author_sort | AMAKIRI OKILO FRIDAY |
collection | DOAJ |
description |
This research work presents the reliability assessment of electrical load distribution system in Federal University of Petroleum Resources, Effurun (FUPRE), Warri using the Analytical method and ETAP software as the simulation tool to run the reliability assessment of the System. The analytical analysis was conceded out by using August 2018 – August 2019 historical data of Tetfund Classrooms Blocks, Hostels, College of Technology, Administration Block, Health Center, and College of Science Feeder obtained from the Benin Electricity Distribution Company [BEDC]. The results conceded revealed that College of Technology Injection Substation is the most reliable in the distribution network when compared to the other five substations around the institution premises as it recorded system indices of ASAI: 99.30, SAIFI: 1.10, SAIDI: 55.35, CAIDI: 123.04 in August 2018 to August 2019. Nevertheless, the total reliability indices of the six substations under investigation as obtained from the analysis, and it shows that availability of power to FUPRE distribution is very poor as compared with the benchmark of IEEE ASAI of 99.99 for distribution substation availability.
|
first_indexed | 2024-03-07T17:28:10Z |
format | Article |
id | doaj.art-6627e6ecd1fc40b1b464d99b4499e348 |
institution | Directory Open Access Journal |
issn | 2068-7559 2344-4932 |
language | English |
last_indexed | 2024-04-24T08:00:29Z |
publishDate | 2020-07-01 |
publisher | Alma Mater Publishing House "Vasile Alecsandri" University of Bacau |
record_format | Article |
series | Journal of Engineering Studies and Research |
spelling | doaj.art-6627e6ecd1fc40b1b464d99b4499e3482024-04-17T19:35:03ZengAlma Mater Publishing House "Vasile Alecsandri" University of BacauJournal of Engineering Studies and Research2068-75592344-49322020-07-01263ELECTRICAL LOAD RELIABILITY ASSESSMENT USING ANALYTICAL METHOD, CASE STUDY: FUPRE 1 X 2.5MVA INJECTION SUBSTATIONAMAKIRI OKILO FRIDAYOSHEVIRE PATRICK This research work presents the reliability assessment of electrical load distribution system in Federal University of Petroleum Resources, Effurun (FUPRE), Warri using the Analytical method and ETAP software as the simulation tool to run the reliability assessment of the System. The analytical analysis was conceded out by using August 2018 – August 2019 historical data of Tetfund Classrooms Blocks, Hostels, College of Technology, Administration Block, Health Center, and College of Science Feeder obtained from the Benin Electricity Distribution Company [BEDC]. The results conceded revealed that College of Technology Injection Substation is the most reliable in the distribution network when compared to the other five substations around the institution premises as it recorded system indices of ASAI: 99.30, SAIFI: 1.10, SAIDI: 55.35, CAIDI: 123.04 in August 2018 to August 2019. Nevertheless, the total reliability indices of the six substations under investigation as obtained from the analysis, and it shows that availability of power to FUPRE distribution is very poor as compared with the benchmark of IEEE ASAI of 99.99 for distribution substation availability. https://jesr.ub.ro/1/article/view/205reliability assessment, availability of power, distribution system, reliability indices, load point indices, system indices and ETAP |
spellingShingle | AMAKIRI OKILO FRIDAY OSHEVIRE PATRICK ELECTRICAL LOAD RELIABILITY ASSESSMENT USING ANALYTICAL METHOD, CASE STUDY: FUPRE 1 X 2.5MVA INJECTION SUBSTATION Journal of Engineering Studies and Research reliability assessment, availability of power, distribution system, reliability indices, load point indices, system indices and ETAP |
title | ELECTRICAL LOAD RELIABILITY ASSESSMENT USING ANALYTICAL METHOD, CASE STUDY: FUPRE 1 X 2.5MVA INJECTION SUBSTATION |
title_full | ELECTRICAL LOAD RELIABILITY ASSESSMENT USING ANALYTICAL METHOD, CASE STUDY: FUPRE 1 X 2.5MVA INJECTION SUBSTATION |
title_fullStr | ELECTRICAL LOAD RELIABILITY ASSESSMENT USING ANALYTICAL METHOD, CASE STUDY: FUPRE 1 X 2.5MVA INJECTION SUBSTATION |
title_full_unstemmed | ELECTRICAL LOAD RELIABILITY ASSESSMENT USING ANALYTICAL METHOD, CASE STUDY: FUPRE 1 X 2.5MVA INJECTION SUBSTATION |
title_short | ELECTRICAL LOAD RELIABILITY ASSESSMENT USING ANALYTICAL METHOD, CASE STUDY: FUPRE 1 X 2.5MVA INJECTION SUBSTATION |
title_sort | electrical load reliability assessment using analytical method case study fupre 1 x 2 5mva injection substation |
topic | reliability assessment, availability of power, distribution system, reliability indices, load point indices, system indices and ETAP |
url | https://jesr.ub.ro/1/article/view/205 |
work_keys_str_mv | AT amakiriokilofriday electricalloadreliabilityassessmentusinganalyticalmethodcasestudyfupre1x25mvainjectionsubstation AT oshevirepatrick electricalloadreliabilityassessmentusinganalyticalmethodcasestudyfupre1x25mvainjectionsubstation |