OPTIMAL PARAMETERS OF BLASTING IN TUNNELS USING PATRONED AND PUMPED EXPLOSIVES WITH ELECTRIC AND NON-ELECTRIC INITIATION
The parameters of drilling and blasting procedures during excavation of Grič and mala Kapela Tunnels are presented in this work. The tunnels are being constructed according to NATM (New Austrian Tunneling Method) in two parallel tubes. By Comparison of blasting with patroned and pumped explosives an...
Main Authors: | , , |
---|---|
Format: | Article |
Language: | English |
Published: |
Faculty of Mining, Geology and Petroleum Engineering
2003-12-01
|
Series: | Rudarsko-geološko-naftni Zbornik |
Subjects: | |
Online Access: | http://hrcak.srce.hr/index.php?show=clanak&id_clanak_jezik=20512&lang=en |
Summary: | The parameters of drilling and blasting procedures during excavation of Grič and mala Kapela Tunnels are presented in this work. The tunnels are being constructed according to NATM (New Austrian Tunneling Method) in two parallel tubes. By Comparison of blasting with patroned and pumped explosives and electric and non-electric mode of initiation, optimal technological parameters have been defined concerning duration of blasting working cycle, progress, tunnel category and seismic effects of blasting on the tunnel support system of the parallel tunnel tube. |
---|---|
ISSN: | 0353-4529 1849-0409 |