ÖĞRENME ETKİLİ HAZIRLIK VE TAŞIMA ZAMANLI PARALEL MAKİNELİ ÇİZELGELEME PROBLEMİ
In studies on scheduling problems, generally setup times and removal times of jobs have been neglected or by including those into processing times solution approaches have been developed. However, as setup times and removal times may be too important to be neglected in some production systems, it...
Main Authors: | , |
---|---|
Format: | Article |
Language: | English |
Published: |
Turkish Air Force Academy
2006-07-01
|
Series: | Havacılık ve Uzay Teknolojileri Dergisi |
Subjects: | |
Online Access: | http://www.jast.hho.edu.tr/JAST/index.php/JAST/article/view/148/136 |
Summary: | In studies on scheduling problems, generally setup times and removal times of jobs have been neglected or by
including those into processing times solution approaches have been developed. However, as setup times and
removal times may be too important to be neglected in some production systems, it may also be necessary to
consider processing times independent from setup times and removal times. Since, in general jobs are done
according to automatic machine processes in production systems processing times do not differ according to
process sequence. But, since human factor becomes influential when setup times and removal times are taken
into consideration, setup times will be decreasing by repeating setup processes frequently. This fact is defined
with learning effect in scheduling literature. In this study, the problem to be examined is minimizing total flow
time when setup times and removal times with learning effect in m-parallel machine scheduling. According to
our research, this is the first study in which setup times and removal times with learning effect in parallel
machine scheduling. |
---|---|