The Construction Methods and Control Mechanisms for Subway Station Undercrossing an Existing Tunnel at Zero Distance

The existing tunnel will inevitably be disturbed when the new subway station is constructed cross under it at zero distance. Three innovative construction schemes were proposed, their effects on deformation control were compared by numerical simulations, and the mechanism of the influence of differe...

Full description

Bibliographic Details
Main Authors: Zihan Zhou, Xiaohan Zhou, Longping Li, Xinrong Liu, Linfeng Wang, Ziqiang Wang
Format: Article
Language:English
Published: MDPI AG 2023-07-01
Series:Applied Sciences
Subjects:
Online Access:https://www.mdpi.com/2076-3417/13/15/8826
_version_ 1797587092022231040
author Zihan Zhou
Xiaohan Zhou
Longping Li
Xinrong Liu
Linfeng Wang
Ziqiang Wang
author_facet Zihan Zhou
Xiaohan Zhou
Longping Li
Xinrong Liu
Linfeng Wang
Ziqiang Wang
author_sort Zihan Zhou
collection DOAJ
description The existing tunnel will inevitably be disturbed when the new subway station is constructed cross under it at zero distance. Three innovative construction schemes were proposed, their effects on deformation control were compared by numerical simulations, and the mechanism of the influence of different tunnel support and excavation methods on the deformation control in them was further explored in order to seek a better scheme in this paper. The results show that the settlement of the existing tunnel in Scheme I (L-type beam + full-face excavation) is the greatest, and that the one in Scheme III (temporary steel column + double-pilot tunnel) is the smallest, but the settlement during excavation changes significantly, along with the large deformation on the side walls of the undercrossing area. Scheme III is not recommended because it is difficult to control and the construction effect is mediocre. Due to the existence of a large free face, the settlement of both sides of the existing tunnel is larger when the L-type beam supports the tunnel, and the bottom of the middle wall bears large compressive stress. The settlement of the existing tunnel excavated by the double-pilot tunneling method is less than that of the full-face tunneling method under the same tunneling support method, and the increase in settlement during the tunneling with the L-type beams is greater than that with the pier columns. In comprehensive consideration, Scheme II (pier column + double-pilot tunnel method) or combined pier column + double-pilot tunnel can control the deformation better.
first_indexed 2024-03-11T00:31:23Z
format Article
id doaj.art-7341c79267ee4ccab57f6dc202eec348
institution Directory Open Access Journal
issn 2076-3417
language English
last_indexed 2024-03-11T00:31:23Z
publishDate 2023-07-01
publisher MDPI AG
record_format Article
series Applied Sciences
spelling doaj.art-7341c79267ee4ccab57f6dc202eec3482023-11-18T22:38:06ZengMDPI AGApplied Sciences2076-34172023-07-011315882610.3390/app13158826The Construction Methods and Control Mechanisms for Subway Station Undercrossing an Existing Tunnel at Zero DistanceZihan Zhou0Xiaohan Zhou1Longping Li2Xinrong Liu3Linfeng Wang4Ziqiang Wang5School of Civil Engineering, Chongqing University, Chongqing 400045, ChinaSchool of Civil Engineering, Chongqing University, Chongqing 400045, ChinaChina Railway Major Bridge Reconnaissance & Design Institute Co., Ltd., Wuhan 430056, ChinaSchool of Civil Engineering, Chongqing University, Chongqing 400045, ChinaSchool of Civil Engineering, Chongqing University, Chongqing 400045, ChinaSchool of Civil Engineering, Chongqing University, Chongqing 400045, ChinaThe existing tunnel will inevitably be disturbed when the new subway station is constructed cross under it at zero distance. Three innovative construction schemes were proposed, their effects on deformation control were compared by numerical simulations, and the mechanism of the influence of different tunnel support and excavation methods on the deformation control in them was further explored in order to seek a better scheme in this paper. The results show that the settlement of the existing tunnel in Scheme I (L-type beam + full-face excavation) is the greatest, and that the one in Scheme III (temporary steel column + double-pilot tunnel) is the smallest, but the settlement during excavation changes significantly, along with the large deformation on the side walls of the undercrossing area. Scheme III is not recommended because it is difficult to control and the construction effect is mediocre. Due to the existence of a large free face, the settlement of both sides of the existing tunnel is larger when the L-type beam supports the tunnel, and the bottom of the middle wall bears large compressive stress. The settlement of the existing tunnel excavated by the double-pilot tunneling method is less than that of the full-face tunneling method under the same tunneling support method, and the increase in settlement during the tunneling with the L-type beams is greater than that with the pier columns. In comprehensive consideration, Scheme II (pier column + double-pilot tunnel method) or combined pier column + double-pilot tunnel can control the deformation better.https://www.mdpi.com/2076-3417/13/15/8826subway station excavationzero-distance undercrossingexisting metro tunneldeformation controlnumerical simulation
spellingShingle Zihan Zhou
Xiaohan Zhou
Longping Li
Xinrong Liu
Linfeng Wang
Ziqiang Wang
The Construction Methods and Control Mechanisms for Subway Station Undercrossing an Existing Tunnel at Zero Distance
Applied Sciences
subway station excavation
zero-distance undercrossing
existing metro tunnel
deformation control
numerical simulation
title The Construction Methods and Control Mechanisms for Subway Station Undercrossing an Existing Tunnel at Zero Distance
title_full The Construction Methods and Control Mechanisms for Subway Station Undercrossing an Existing Tunnel at Zero Distance
title_fullStr The Construction Methods and Control Mechanisms for Subway Station Undercrossing an Existing Tunnel at Zero Distance
title_full_unstemmed The Construction Methods and Control Mechanisms for Subway Station Undercrossing an Existing Tunnel at Zero Distance
title_short The Construction Methods and Control Mechanisms for Subway Station Undercrossing an Existing Tunnel at Zero Distance
title_sort construction methods and control mechanisms for subway station undercrossing an existing tunnel at zero distance
topic subway station excavation
zero-distance undercrossing
existing metro tunnel
deformation control
numerical simulation
url https://www.mdpi.com/2076-3417/13/15/8826
work_keys_str_mv AT zihanzhou theconstructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance
AT xiaohanzhou theconstructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance
AT longpingli theconstructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance
AT xinrongliu theconstructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance
AT linfengwang theconstructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance
AT ziqiangwang theconstructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance
AT zihanzhou constructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance
AT xiaohanzhou constructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance
AT longpingli constructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance
AT xinrongliu constructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance
AT linfengwang constructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance
AT ziqiangwang constructionmethodsandcontrolmechanismsforsubwaystationundercrossinganexistingtunnelatzerodistance