Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP
Public sector projects in KP suffers time delays leading to years of delay and cost overrun of over Rs25 billion, surprisingly close to half of this amount i.e. 11.2 billion is reported in the health sector projects in KP. This paper therefore, explores factors leading to time and cost overrun in th...
Main Authors: | , , |
---|---|
Format: | Article |
Language: | English |
Published: |
Institute of Business Management
2019-12-01
|
Series: | International Journal of Experiential Learning & Case Studies |
Subjects: | |
Online Access: | http://jmsnew.iobmresearch.com/index.php/ijelcs/article/view/288 |
_version_ | 1797868359784595456 |
---|---|
author | Shahnawaz Khan Muhammad Zaffar Waqar Ahmad |
author_facet | Shahnawaz Khan Muhammad Zaffar Waqar Ahmad |
author_sort | Shahnawaz Khan |
collection | DOAJ |
description | Public sector projects in KP suffers time delays leading to years of delay and cost overrun of over Rs25 billion, surprisingly close to half of this amount i.e. 11.2 billion is reported in the health sector projects in KP. This paper therefore, explores factors leading to time and cost overrun in the construction and IT projects of Health Department Peshawar, Government of KPK, Pakistan. To explore the causes of cost and time overrun, the study utilized Yin’s case study model thus collecting data through qualitative semi-structured interviews. The study used Miles and Huberman (1994) approach of thematic modelling for data analysis. The finding reveals that factors leading to time and cost overrun are administrative issues, delays in fund release, political Issues, monitoring &control, work site issues, inflationary effects, poor cost estimation, issues from contractor’s side, stakeholders and IT issues. While, certain factors causing overrun in specific to IT projects are resistance by the stakeholders for change, lack of understanding on the part of consumer about the benefit of the project and rapid changes in technology. |
first_indexed | 2024-04-09T23:54:42Z |
format | Article |
id | doaj.art-742d3c67c819495aa992ab90508be511 |
institution | Directory Open Access Journal |
issn | 2520-4475 2521-9359 |
language | English |
last_indexed | 2024-04-09T23:54:42Z |
publishDate | 2019-12-01 |
publisher | Institute of Business Management |
record_format | Article |
series | International Journal of Experiential Learning & Case Studies |
spelling | doaj.art-742d3c67c819495aa992ab90508be5112023-03-17T03:43:34ZengInstitute of Business ManagementInternational Journal of Experiential Learning & Case Studies2520-44752521-93592019-12-0142269277288Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KPShahnawaz KhanMuhammad ZaffarWaqar AhmadPublic sector projects in KP suffers time delays leading to years of delay and cost overrun of over Rs25 billion, surprisingly close to half of this amount i.e. 11.2 billion is reported in the health sector projects in KP. This paper therefore, explores factors leading to time and cost overrun in the construction and IT projects of Health Department Peshawar, Government of KPK, Pakistan. To explore the causes of cost and time overrun, the study utilized Yin’s case study model thus collecting data through qualitative semi-structured interviews. The study used Miles and Huberman (1994) approach of thematic modelling for data analysis. The finding reveals that factors leading to time and cost overrun are administrative issues, delays in fund release, political Issues, monitoring &control, work site issues, inflationary effects, poor cost estimation, issues from contractor’s side, stakeholders and IT issues. While, certain factors causing overrun in specific to IT projects are resistance by the stakeholders for change, lack of understanding on the part of consumer about the benefit of the project and rapid changes in technology.http://jmsnew.iobmresearch.com/index.php/ijelcs/article/view/288cost overrun time overruns public sector projects construction projects, it projects |
spellingShingle | Shahnawaz Khan Muhammad Zaffar Waqar Ahmad Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP International Journal of Experiential Learning & Case Studies cost overrun time overruns public sector projects construction projects, it projects |
title | Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP |
title_full | Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP |
title_fullStr | Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP |
title_full_unstemmed | Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP |
title_short | Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP |
title_sort | causes of time and cost overrun a case study of health sector projects in peshawar kp |
topic | cost overrun time overruns public sector projects construction projects, it projects |
url | http://jmsnew.iobmresearch.com/index.php/ijelcs/article/view/288 |
work_keys_str_mv | AT shahnawazkhan causesoftimeandcostoverrunacasestudyofhealthsectorprojectsinpeshawarkp AT muhammadzaffar causesoftimeandcostoverrunacasestudyofhealthsectorprojectsinpeshawarkp AT waqarahmad causesoftimeandcostoverrunacasestudyofhealthsectorprojectsinpeshawarkp |