Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP

Public sector projects in KP suffers time delays leading to years of delay and cost overrun of over Rs25 billion, surprisingly close to half of this amount i.e. 11.2 billion is reported in the health sector projects in KP. This paper therefore, explores factors leading to time and cost overrun in th...

Full description

Bibliographic Details
Main Authors: Shahnawaz Khan, Muhammad Zaffar, Waqar Ahmad
Format: Article
Language:English
Published: Institute of Business Management 2019-12-01
Series:International Journal of Experiential Learning & Case Studies
Subjects:
Online Access:http://jmsnew.iobmresearch.com/index.php/ijelcs/article/view/288
_version_ 1797868359784595456
author Shahnawaz Khan
Muhammad Zaffar
Waqar Ahmad
author_facet Shahnawaz Khan
Muhammad Zaffar
Waqar Ahmad
author_sort Shahnawaz Khan
collection DOAJ
description Public sector projects in KP suffers time delays leading to years of delay and cost overrun of over Rs25 billion, surprisingly close to half of this amount i.e. 11.2 billion is reported in the health sector projects in KP. This paper therefore, explores factors leading to time and cost overrun in the construction and IT projects of Health Department Peshawar, Government of KPK, Pakistan. To explore the causes of cost and time overrun, the study utilized Yin’s case study model thus collecting data through qualitative semi-structured interviews. The study used Miles and Huberman (1994) approach of thematic modelling for data analysis. The finding reveals that factors leading to time and cost overrun are administrative issues, delays in fund release, political Issues, monitoring &control, work site issues, inflationary effects, poor cost estimation, issues from contractor’s side, stakeholders and IT issues. While, certain factors causing overrun in specific to IT projects are resistance by the stakeholders for change, lack of understanding on the part of consumer about the benefit of the project and rapid changes in technology.
first_indexed 2024-04-09T23:54:42Z
format Article
id doaj.art-742d3c67c819495aa992ab90508be511
institution Directory Open Access Journal
issn 2520-4475
2521-9359
language English
last_indexed 2024-04-09T23:54:42Z
publishDate 2019-12-01
publisher Institute of Business Management
record_format Article
series International Journal of Experiential Learning & Case Studies
spelling doaj.art-742d3c67c819495aa992ab90508be5112023-03-17T03:43:34ZengInstitute of Business ManagementInternational Journal of Experiential Learning & Case Studies2520-44752521-93592019-12-0142269277288Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KPShahnawaz KhanMuhammad ZaffarWaqar AhmadPublic sector projects in KP suffers time delays leading to years of delay and cost overrun of over Rs25 billion, surprisingly close to half of this amount i.e. 11.2 billion is reported in the health sector projects in KP. This paper therefore, explores factors leading to time and cost overrun in the construction and IT projects of Health Department Peshawar, Government of KPK, Pakistan. To explore the causes of cost and time overrun, the study utilized Yin’s case study model thus collecting data through qualitative semi-structured interviews. The study used Miles and Huberman (1994) approach of thematic modelling for data analysis. The finding reveals that factors leading to time and cost overrun are administrative issues, delays in fund release, political Issues, monitoring &control, work site issues, inflationary effects, poor cost estimation, issues from contractor’s side, stakeholders and IT issues. While, certain factors causing overrun in specific to IT projects are resistance by the stakeholders for change, lack of understanding on the part of consumer about the benefit of the project and rapid changes in technology.http://jmsnew.iobmresearch.com/index.php/ijelcs/article/view/288cost overrun time overruns public sector projects construction projects, it projects
spellingShingle Shahnawaz Khan
Muhammad Zaffar
Waqar Ahmad
Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP
International Journal of Experiential Learning & Case Studies
cost overrun
time overruns
public sector projects
construction projects,
it projects
title Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP
title_full Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP
title_fullStr Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP
title_full_unstemmed Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP
title_short Causes of Time and Cost Overrun: A Case Study of Health Sector Projects in Peshawar, KP
title_sort causes of time and cost overrun a case study of health sector projects in peshawar kp
topic cost overrun
time overruns
public sector projects
construction projects,
it projects
url http://jmsnew.iobmresearch.com/index.php/ijelcs/article/view/288
work_keys_str_mv AT shahnawazkhan causesoftimeandcostoverrunacasestudyofhealthsectorprojectsinpeshawarkp
AT muhammadzaffar causesoftimeandcostoverrunacasestudyofhealthsectorprojectsinpeshawarkp
AT waqarahmad causesoftimeandcostoverrunacasestudyofhealthsectorprojectsinpeshawarkp