Displacement Characteristics of Shallow-Buried Large-Section Loess Tunnel with Different Types of Pre-Supports: A Case Study of New Badaling Tunnel
Three-bench seven-step excavation method (TSEM) has been widely used in large-section loess tunnels for high-speed railway in China. As the most commonly applied pre-supports, pipe roofs and leading ductules are broadly used in the ground reinforcement of loess tunnels. Their application is to ensur...
Main Authors: | , , , , , |
---|---|
Format: | Article |
Language: | English |
Published: |
MDPI AG
2019-12-01
|
Series: | Applied Sciences |
Subjects: | |
Online Access: | https://www.mdpi.com/2076-3417/10/1/195 |
_version_ | 1818384558214610944 |
---|---|
author | Daoping Liu Dingli Zhang Qian Fang Zhenyu Sun Liqiang Cao Ao Li |
author_facet | Daoping Liu Dingli Zhang Qian Fang Zhenyu Sun Liqiang Cao Ao Li |
author_sort | Daoping Liu |
collection | DOAJ |
description | Three-bench seven-step excavation method (TSEM) has been widely used in large-section loess tunnels for high-speed railway in China. As the most commonly applied pre-supports, pipe roofs and leading ductules are broadly used in the ground reinforcement of loess tunnels. Their application is to ensure face stability and prevent tunnel collapse during construction. This study focused on the impacts of the TSEM on the ground surface settlement (GSS), as well as the tunnel displacement characteristics for the high-speed railway tunnels with large cross-sections in loess ground. Furthermore, the reinforcement effects of the two kinds of pre-supports were compared in this study. In-situ tests for a total of 12 sections were conducted to reveal the GSSs and displacement characteristics for the shallow-buried large-section loess tunnels. The monitoring results showed that the excavation process plays a significant role on the GSSs and tunnel displacements. A maximum value was observed for the tunnel displacement rate at the excavation of the upper and middle benches, where the face instability or collapse were prone to occur. The GSS trough curves were deviated to the early excavation side, with no conformation to the Gauss distribution. After a series of comparisons, we concluded that the pre-reinforcement effect of the pipe roof is better than that of the leading ductule for the loess tunnels. |
first_indexed | 2024-12-14T03:24:10Z |
format | Article |
id | doaj.art-76b9330a8c094db3b4896664f0906ae4 |
institution | Directory Open Access Journal |
issn | 2076-3417 |
language | English |
last_indexed | 2024-12-14T03:24:10Z |
publishDate | 2019-12-01 |
publisher | MDPI AG |
record_format | Article |
series | Applied Sciences |
spelling | doaj.art-76b9330a8c094db3b4896664f0906ae42022-12-21T23:18:57ZengMDPI AGApplied Sciences2076-34172019-12-0110119510.3390/app10010195app10010195Displacement Characteristics of Shallow-Buried Large-Section Loess Tunnel with Different Types of Pre-Supports: A Case Study of New Badaling TunnelDaoping Liu0Dingli Zhang1Qian Fang2Zhenyu Sun3Liqiang Cao4Ao Li5Key Laboratory for Urban Underground Engineering of Ministry of Education, Beijing Jiaotong University, Beijing 100044, ChinaKey Laboratory for Urban Underground Engineering of Ministry of Education, Beijing Jiaotong University, Beijing 100044, ChinaKey Laboratory for Urban Underground Engineering of Ministry of Education, Beijing Jiaotong University, Beijing 100044, ChinaKey Laboratory for Urban Underground Engineering of Ministry of Education, Beijing Jiaotong University, Beijing 100044, ChinaKey Laboratory for Urban Underground Engineering of Ministry of Education, Beijing Jiaotong University, Beijing 100044, ChinaKey Laboratory for Urban Underground Engineering of Ministry of Education, Beijing Jiaotong University, Beijing 100044, ChinaThree-bench seven-step excavation method (TSEM) has been widely used in large-section loess tunnels for high-speed railway in China. As the most commonly applied pre-supports, pipe roofs and leading ductules are broadly used in the ground reinforcement of loess tunnels. Their application is to ensure face stability and prevent tunnel collapse during construction. This study focused on the impacts of the TSEM on the ground surface settlement (GSS), as well as the tunnel displacement characteristics for the high-speed railway tunnels with large cross-sections in loess ground. Furthermore, the reinforcement effects of the two kinds of pre-supports were compared in this study. In-situ tests for a total of 12 sections were conducted to reveal the GSSs and displacement characteristics for the shallow-buried large-section loess tunnels. The monitoring results showed that the excavation process plays a significant role on the GSSs and tunnel displacements. A maximum value was observed for the tunnel displacement rate at the excavation of the upper and middle benches, where the face instability or collapse were prone to occur. The GSS trough curves were deviated to the early excavation side, with no conformation to the Gauss distribution. After a series of comparisons, we concluded that the pre-reinforcement effect of the pipe roof is better than that of the leading ductule for the loess tunnels.https://www.mdpi.com/2076-3417/10/1/195loess groundlarge-span tunnelthree-bench seven-step excavation methodpre-supportground surface settlementarch settlementhorizontal convergence |
spellingShingle | Daoping Liu Dingli Zhang Qian Fang Zhenyu Sun Liqiang Cao Ao Li Displacement Characteristics of Shallow-Buried Large-Section Loess Tunnel with Different Types of Pre-Supports: A Case Study of New Badaling Tunnel Applied Sciences loess ground large-span tunnel three-bench seven-step excavation method pre-support ground surface settlement arch settlement horizontal convergence |
title | Displacement Characteristics of Shallow-Buried Large-Section Loess Tunnel with Different Types of Pre-Supports: A Case Study of New Badaling Tunnel |
title_full | Displacement Characteristics of Shallow-Buried Large-Section Loess Tunnel with Different Types of Pre-Supports: A Case Study of New Badaling Tunnel |
title_fullStr | Displacement Characteristics of Shallow-Buried Large-Section Loess Tunnel with Different Types of Pre-Supports: A Case Study of New Badaling Tunnel |
title_full_unstemmed | Displacement Characteristics of Shallow-Buried Large-Section Loess Tunnel with Different Types of Pre-Supports: A Case Study of New Badaling Tunnel |
title_short | Displacement Characteristics of Shallow-Buried Large-Section Loess Tunnel with Different Types of Pre-Supports: A Case Study of New Badaling Tunnel |
title_sort | displacement characteristics of shallow buried large section loess tunnel with different types of pre supports a case study of new badaling tunnel |
topic | loess ground large-span tunnel three-bench seven-step excavation method pre-support ground surface settlement arch settlement horizontal convergence |
url | https://www.mdpi.com/2076-3417/10/1/195 |
work_keys_str_mv | AT daopingliu displacementcharacteristicsofshallowburiedlargesectionloesstunnelwithdifferenttypesofpresupportsacasestudyofnewbadalingtunnel AT dinglizhang displacementcharacteristicsofshallowburiedlargesectionloesstunnelwithdifferenttypesofpresupportsacasestudyofnewbadalingtunnel AT qianfang displacementcharacteristicsofshallowburiedlargesectionloesstunnelwithdifferenttypesofpresupportsacasestudyofnewbadalingtunnel AT zhenyusun displacementcharacteristicsofshallowburiedlargesectionloesstunnelwithdifferenttypesofpresupportsacasestudyofnewbadalingtunnel AT liqiangcao displacementcharacteristicsofshallowburiedlargesectionloesstunnelwithdifferenttypesofpresupportsacasestudyofnewbadalingtunnel AT aoli displacementcharacteristicsofshallowburiedlargesectionloesstunnelwithdifferenttypesofpresupportsacasestudyofnewbadalingtunnel |