A decision-making method to assess the benefits of a semi-mobile in-pit crushing and conveying alternative during the early stages of a mining project
Abstract A significant cost in the operating budget of most mining operations arises from purchasing and maintaining haulage trucks. Recently, in-pit crushing and conveying (IPCC) has been subject to research because of its potential to reduce haulage costs. The objective of this study is to identif...
Main Authors: | , , , , |
---|---|
Format: | Article |
Language: | English |
Published: |
Fundação Gorceix
|
Series: | REM: International Engineering Journal |
Subjects: | |
Online Access: | http://www.scielo.br/scielo.php?script=sci_arttext&pid=S2448-167X2019000300285&lng=en&tlng=en |
_version_ | 1818836646792003584 |
---|---|
author | Rodrigo Augusto Nunes Homero Delboni Junior Giorgio de Tomi Cecília Beatriz Infante Bladen Allan |
author_facet | Rodrigo Augusto Nunes Homero Delboni Junior Giorgio de Tomi Cecília Beatriz Infante Bladen Allan |
author_sort | Rodrigo Augusto Nunes |
collection | DOAJ |
description | Abstract A significant cost in the operating budget of most mining operations arises from purchasing and maintaining haulage trucks. Recently, in-pit crushing and conveying (IPCC) has been subject to research because of its potential to reduce haulage costs. The objective of this study is to identify early on in a project, by means of a decision-making method, whether or not the semi-mobile IPCC (SMIPCC) is an appropriate alternative to the conventional truck haulage method on the loading and hauling approaches. This method is based on cost analysis and the evaluation of environmental impacts, being successfully tested at an existing open-pit mine, where the results indicated that the IPCC was the most cost-effective option for the operation. Although the IPCC's initial CAPEX was 60% higher than the conventional approach, the IPCC's OPEX was 43% lower, resulting in a 28% reduction of the life-of-mine net present cost (NPC). |
first_indexed | 2024-12-19T03:09:55Z |
format | Article |
id | doaj.art-8c68785edb6a4a47a21401d1da46a3a0 |
institution | Directory Open Access Journal |
issn | 2448-167X |
language | English |
last_indexed | 2024-12-19T03:09:55Z |
publisher | Fundação Gorceix |
record_format | Article |
series | REM: International Engineering Journal |
spelling | doaj.art-8c68785edb6a4a47a21401d1da46a3a02022-12-21T20:38:03ZengFundação GorceixREM: International Engineering Journal2448-167X72228529110.1590/0370-44672018720109S2448-167X2019000300285A decision-making method to assess the benefits of a semi-mobile in-pit crushing and conveying alternative during the early stages of a mining projectRodrigo Augusto NunesHomero Delboni JuniorGiorgio de TomiCecília Beatriz InfanteBladen AllanAbstract A significant cost in the operating budget of most mining operations arises from purchasing and maintaining haulage trucks. Recently, in-pit crushing and conveying (IPCC) has been subject to research because of its potential to reduce haulage costs. The objective of this study is to identify early on in a project, by means of a decision-making method, whether or not the semi-mobile IPCC (SMIPCC) is an appropriate alternative to the conventional truck haulage method on the loading and hauling approaches. This method is based on cost analysis and the evaluation of environmental impacts, being successfully tested at an existing open-pit mine, where the results indicated that the IPCC was the most cost-effective option for the operation. Although the IPCC's initial CAPEX was 60% higher than the conventional approach, the IPCC's OPEX was 43% lower, resulting in a 28% reduction of the life-of-mine net present cost (NPC).http://www.scielo.br/scielo.php?script=sci_arttext&pid=S2448-167X2019000300285&lng=en&tlng=ensemi-mobile IPCCcost savingdecision-making methodinitial design studyCO reduction |
spellingShingle | Rodrigo Augusto Nunes Homero Delboni Junior Giorgio de Tomi Cecília Beatriz Infante Bladen Allan A decision-making method to assess the benefits of a semi-mobile in-pit crushing and conveying alternative during the early stages of a mining project REM: International Engineering Journal semi-mobile IPCC cost saving decision-making method initial design study CO reduction |
title | A decision-making method to assess the benefits of a semi-mobile in-pit crushing and conveying alternative during the early stages of a mining project |
title_full | A decision-making method to assess the benefits of a semi-mobile in-pit crushing and conveying alternative during the early stages of a mining project |
title_fullStr | A decision-making method to assess the benefits of a semi-mobile in-pit crushing and conveying alternative during the early stages of a mining project |
title_full_unstemmed | A decision-making method to assess the benefits of a semi-mobile in-pit crushing and conveying alternative during the early stages of a mining project |
title_short | A decision-making method to assess the benefits of a semi-mobile in-pit crushing and conveying alternative during the early stages of a mining project |
title_sort | decision making method to assess the benefits of a semi mobile in pit crushing and conveying alternative during the early stages of a mining project |
topic | semi-mobile IPCC cost saving decision-making method initial design study CO reduction |
url | http://www.scielo.br/scielo.php?script=sci_arttext&pid=S2448-167X2019000300285&lng=en&tlng=en |
work_keys_str_mv | AT rodrigoaugustonunes adecisionmakingmethodtoassessthebenefitsofasemimobileinpitcrushingandconveyingalternativeduringtheearlystagesofaminingproject AT homerodelbonijunior adecisionmakingmethodtoassessthebenefitsofasemimobileinpitcrushingandconveyingalternativeduringtheearlystagesofaminingproject AT giorgiodetomi adecisionmakingmethodtoassessthebenefitsofasemimobileinpitcrushingandconveyingalternativeduringtheearlystagesofaminingproject AT ceciliabeatrizinfante adecisionmakingmethodtoassessthebenefitsofasemimobileinpitcrushingandconveyingalternativeduringtheearlystagesofaminingproject AT bladenallan adecisionmakingmethodtoassessthebenefitsofasemimobileinpitcrushingandconveyingalternativeduringtheearlystagesofaminingproject AT rodrigoaugustonunes decisionmakingmethodtoassessthebenefitsofasemimobileinpitcrushingandconveyingalternativeduringtheearlystagesofaminingproject AT homerodelbonijunior decisionmakingmethodtoassessthebenefitsofasemimobileinpitcrushingandconveyingalternativeduringtheearlystagesofaminingproject AT giorgiodetomi decisionmakingmethodtoassessthebenefitsofasemimobileinpitcrushingandconveyingalternativeduringtheearlystagesofaminingproject AT ceciliabeatrizinfante decisionmakingmethodtoassessthebenefitsofasemimobileinpitcrushingandconveyingalternativeduringtheearlystagesofaminingproject AT bladenallan decisionmakingmethodtoassessthebenefitsofasemimobileinpitcrushingandconveyingalternativeduringtheearlystagesofaminingproject |