Research on Construction Practice of Assembled Substation——A Case in Anhui Xuancheng Xinhang 110kV Substation Project

The assembled substation is a substation construction that is "resource-saving, environment-friendly, and industrialized" through prefabrication and on-site installation. Taking the Xuancheng Xinhang 110kV substation project in Anhui as an example, this paper studies the standardization de...

Full description

Bibliographic Details
Main Authors: Ximing Chen, Dian Bao, Chaojun Qian, Shao-jie Zhang
Format: Article
Language:English
Published: EDP Sciences 2019-01-01
Series:E3S Web of Conferences
Online Access:https://www.e3s-conferences.org/articles/e3sconf/pdf/2019/62/e3sconf_icbte2019_02038.pdf
_version_ 1818338617490145280
author Ximing Chen
Dian Bao
Chaojun Qian
Shao-jie Zhang
author_facet Ximing Chen
Dian Bao
Chaojun Qian
Shao-jie Zhang
author_sort Ximing Chen
collection DOAJ
description The assembled substation is a substation construction that is "resource-saving, environment-friendly, and industrialized" through prefabrication and on-site installation. Taking the Xuancheng Xinhang 110kV substation project in Anhui as an example, this paper studies the standardization development of assembled industrial buildings and substations at home and abroad, points out the problems existing in the construction and buildingpractice of the assembled substation, and puts forward relevant suggestions for these problems.
first_indexed 2024-12-13T15:13:58Z
format Article
id doaj.art-ab553648ed674ba79ad6b4b3073e0397
institution Directory Open Access Journal
issn 2267-1242
language English
last_indexed 2024-12-13T15:13:58Z
publishDate 2019-01-01
publisher EDP Sciences
record_format Article
series E3S Web of Conferences
spelling doaj.art-ab553648ed674ba79ad6b4b3073e03972022-12-21T23:40:46ZengEDP SciencesE3S Web of Conferences2267-12422019-01-011360203810.1051/e3sconf/201913602038e3sconf_icbte2019_02038Research on Construction Practice of Assembled Substation——A Case in Anhui Xuancheng Xinhang 110kV Substation ProjectXiming Chen0Dian Bao1Chaojun Qian2Shao-jie Zhang3Anhui Electric Power Engineering Supervision Co., Ltd.State Grid XuanCheng Electric Power Co., Ltd.State Grid Anhui Electric Power Co., Ltd.Construction CompanyAnhui Jianzhu University, BIM Engineering Center of Anhui ProvinceThe assembled substation is a substation construction that is "resource-saving, environment-friendly, and industrialized" through prefabrication and on-site installation. Taking the Xuancheng Xinhang 110kV substation project in Anhui as an example, this paper studies the standardization development of assembled industrial buildings and substations at home and abroad, points out the problems existing in the construction and buildingpractice of the assembled substation, and puts forward relevant suggestions for these problems.https://www.e3s-conferences.org/articles/e3sconf/pdf/2019/62/e3sconf_icbte2019_02038.pdf
spellingShingle Ximing Chen
Dian Bao
Chaojun Qian
Shao-jie Zhang
Research on Construction Practice of Assembled Substation——A Case in Anhui Xuancheng Xinhang 110kV Substation Project
E3S Web of Conferences
title Research on Construction Practice of Assembled Substation——A Case in Anhui Xuancheng Xinhang 110kV Substation Project
title_full Research on Construction Practice of Assembled Substation——A Case in Anhui Xuancheng Xinhang 110kV Substation Project
title_fullStr Research on Construction Practice of Assembled Substation——A Case in Anhui Xuancheng Xinhang 110kV Substation Project
title_full_unstemmed Research on Construction Practice of Assembled Substation——A Case in Anhui Xuancheng Xinhang 110kV Substation Project
title_short Research on Construction Practice of Assembled Substation——A Case in Anhui Xuancheng Xinhang 110kV Substation Project
title_sort research on construction practice of assembled substation a case in anhui xuancheng xinhang 110kv substation project
url https://www.e3s-conferences.org/articles/e3sconf/pdf/2019/62/e3sconf_icbte2019_02038.pdf
work_keys_str_mv AT ximingchen researchonconstructionpracticeofassembledsubstationacaseinanhuixuanchengxinhang110kvsubstationproject
AT dianbao researchonconstructionpracticeofassembledsubstationacaseinanhuixuanchengxinhang110kvsubstationproject
AT chaojunqian researchonconstructionpracticeofassembledsubstationacaseinanhuixuanchengxinhang110kvsubstationproject
AT shaojiezhang researchonconstructionpracticeofassembledsubstationacaseinanhuixuanchengxinhang110kvsubstationproject