Optimal Re-Dispatching of Cascaded Hydropower Plants Using Quadratic Programming and Chance-Constrained Programming
Stochastic production from wind power plants imposes additional uncertainty in power system operation. It can cause problems in load and generation balancing in the power system and can also cause congestion in the transmission network. This paper deals with the problems of congestion in the transmi...
Main Authors: | , , , |
---|---|
Format: | Article |
Language: | English |
Published: |
MDPI AG
2019-04-01
|
Series: | Energies |
Subjects: | |
Online Access: | https://www.mdpi.com/1996-1073/12/9/1604 |
_version_ | 1798025381730582528 |
---|---|
author | Krešimir Fekete Srete Nikolovski Zvonimir Klaić Ana Androjić |
author_facet | Krešimir Fekete Srete Nikolovski Zvonimir Klaić Ana Androjić |
author_sort | Krešimir Fekete |
collection | DOAJ |
description | Stochastic production from wind power plants imposes additional uncertainty in power system operation. It can cause problems in load and generation balancing in the power system and can also cause congestion in the transmission network. This paper deals with the problems of congestion in the transmission network, which are caused by the production of wind power plants. An optimization model for corrective congestion management is developed. Congestions are relieved by re-dispatching several cascaded hydropower plants. Optimization methodology covers the optimization period of one day divided into the 24 segments for each hour. The developed optimization methodology consists of two optimization stages. The objective of the first optimization stage is to obtain an optimal day-ahead dispatch plan of the hydropower plants that maximizes profit from selling energy to the day-ahead electricity market. If such a dispatch plan, together with the wind power plant production, causes congestion in the transmission network, the second optimization stage is started. The objective of the second optimization stage is the minimization of the re-dispatching of cascaded hydropower plants in order to avoid possible congestion. The concept of chance-constrained programming is used in order to consider uncertain wind power production. The first optimization stage is defined as a mixed-integer linear programming problem and the second optimization stage is defined as a quadratic programming (QP) problem, in combination with chance-constrained programming. The developed optimization model is tested and verified using the model of a real-life power system. |
first_indexed | 2024-04-11T18:17:54Z |
format | Article |
id | doaj.art-ae196a50173d4424a4a2c04f1c99042f |
institution | Directory Open Access Journal |
issn | 1996-1073 |
language | English |
last_indexed | 2024-04-11T18:17:54Z |
publishDate | 2019-04-01 |
publisher | MDPI AG |
record_format | Article |
series | Energies |
spelling | doaj.art-ae196a50173d4424a4a2c04f1c99042f2022-12-22T04:09:51ZengMDPI AGEnergies1996-10732019-04-01129160410.3390/en12091604en12091604Optimal Re-Dispatching of Cascaded Hydropower Plants Using Quadratic Programming and Chance-Constrained ProgrammingKrešimir Fekete0Srete Nikolovski1Zvonimir Klaić2Ana Androjić3Faculty of Electrical Engineering, Computer Science and Information Technology Osijek, Josip Juraj Strossmayer University of Osijek, 31000 Osijek, CroatiaFaculty of Electrical Engineering, Computer Science and Information Technology Osijek, Josip Juraj Strossmayer University of Osijek, 31000 Osijek, CroatiaFaculty of Electrical Engineering, Computer Science and Information Technology Osijek, Josip Juraj Strossmayer University of Osijek, 31000 Osijek, CroatiaHEP Proizvodnja d.o.o., 10000 Zagreb, CroatiaStochastic production from wind power plants imposes additional uncertainty in power system operation. It can cause problems in load and generation balancing in the power system and can also cause congestion in the transmission network. This paper deals with the problems of congestion in the transmission network, which are caused by the production of wind power plants. An optimization model for corrective congestion management is developed. Congestions are relieved by re-dispatching several cascaded hydropower plants. Optimization methodology covers the optimization period of one day divided into the 24 segments for each hour. The developed optimization methodology consists of two optimization stages. The objective of the first optimization stage is to obtain an optimal day-ahead dispatch plan of the hydropower plants that maximizes profit from selling energy to the day-ahead electricity market. If such a dispatch plan, together with the wind power plant production, causes congestion in the transmission network, the second optimization stage is started. The objective of the second optimization stage is the minimization of the re-dispatching of cascaded hydropower plants in order to avoid possible congestion. The concept of chance-constrained programming is used in order to consider uncertain wind power production. The first optimization stage is defined as a mixed-integer linear programming problem and the second optimization stage is defined as a quadratic programming (QP) problem, in combination with chance-constrained programming. The developed optimization model is tested and verified using the model of a real-life power system.https://www.mdpi.com/1996-1073/12/9/1604hydropower plantwind power plantquadratic programmingchance-constrainedcongestiontransmission system |
spellingShingle | Krešimir Fekete Srete Nikolovski Zvonimir Klaić Ana Androjić Optimal Re-Dispatching of Cascaded Hydropower Plants Using Quadratic Programming and Chance-Constrained Programming Energies hydropower plant wind power plant quadratic programming chance-constrained congestion transmission system |
title | Optimal Re-Dispatching of Cascaded Hydropower Plants Using Quadratic Programming and Chance-Constrained Programming |
title_full | Optimal Re-Dispatching of Cascaded Hydropower Plants Using Quadratic Programming and Chance-Constrained Programming |
title_fullStr | Optimal Re-Dispatching of Cascaded Hydropower Plants Using Quadratic Programming and Chance-Constrained Programming |
title_full_unstemmed | Optimal Re-Dispatching of Cascaded Hydropower Plants Using Quadratic Programming and Chance-Constrained Programming |
title_short | Optimal Re-Dispatching of Cascaded Hydropower Plants Using Quadratic Programming and Chance-Constrained Programming |
title_sort | optimal re dispatching of cascaded hydropower plants using quadratic programming and chance constrained programming |
topic | hydropower plant wind power plant quadratic programming chance-constrained congestion transmission system |
url | https://www.mdpi.com/1996-1073/12/9/1604 |
work_keys_str_mv | AT kresimirfekete optimalredispatchingofcascadedhydropowerplantsusingquadraticprogrammingandchanceconstrainedprogramming AT sretenikolovski optimalredispatchingofcascadedhydropowerplantsusingquadraticprogrammingandchanceconstrainedprogramming AT zvonimirklaic optimalredispatchingofcascadedhydropowerplantsusingquadraticprogrammingandchanceconstrainedprogramming AT anaandrojic optimalredispatchingofcascadedhydropowerplantsusingquadraticprogrammingandchanceconstrainedprogramming |