Solving resource-constrained construction scheduling problems with overlaps by metaheuristic

The paper concerns the problem of roadworks scheduling executed in the flow-shop system. Works may be performed parallelly with the acceleration (overlaps) of construction project, i.e. the following work on the assembly line can begin before the completion of the predecessor work. Taking into accou...

Full description

Bibliographic Details
Main Authors: Wojciech Bożejko, Zdzisław Hejducki, Mariusz Uchroński, Mieczysław Wodecki
Format: Article
Language:English
Published: Vilnius Gediminas Technical University 2014-07-01
Series:Journal of Civil Engineering and Management
Subjects:
Online Access:http://journals.vgtu.lt/index.php/JCEM/article/view/3159
_version_ 1818875058331844608
author Wojciech Bożejko
Zdzisław Hejducki
Mariusz Uchroński
Mieczysław Wodecki
author_facet Wojciech Bożejko
Zdzisław Hejducki
Mariusz Uchroński
Mieczysław Wodecki
author_sort Wojciech Bożejko
collection DOAJ
description The paper concerns the problem of roadworks scheduling executed in the flow-shop system. Works may be performed parallelly with the acceleration (overlaps) of construction project, i.e. the following work on the assembly line can begin before the completion of the predecessor work. Taking into account the acceleration enables accurate modeling of complex real construction processes. The above fact can greatly shorten the time of realization of construction process which has a direct impact on reducing costs. The considered issue belongs to the class of NP-hard problems. We introduce the new: mathematical model, specific properties as an acceleration tools, as well as two new optimization algorithms for the problem considered: construction and tabu search. The execution of algorithms was illustrated on the example of a case study concerning the construction of roads. They were also verified on the examples taken from the literature and on already completed construction processes. The obtained results are fully satisfactory. The assigned execution times are close to optimal. The presented methods allow its practitioners (both the planners and the managers) to include in the model the acceleration of the works and the design of a much more efficient construction scheduling. The presented new scheduling method leads to a more competitive environment for contraction companies.
first_indexed 2024-12-19T13:20:27Z
format Article
id doaj.art-cb5ef820243849b296b732f6ab386bbb
institution Directory Open Access Journal
issn 1392-3730
1822-3605
language English
last_indexed 2024-12-19T13:20:27Z
publishDate 2014-07-01
publisher Vilnius Gediminas Technical University
record_format Article
series Journal of Civil Engineering and Management
spelling doaj.art-cb5ef820243849b296b732f6ab386bbb2022-12-21T20:19:44ZengVilnius Gediminas Technical UniversityJournal of Civil Engineering and Management1392-37301822-36052014-07-0120510.3846/13923730.2014.906496Solving resource-constrained construction scheduling problems with overlaps by metaheuristicWojciech Bożejko0Zdzisław Hejducki1Mariusz Uchroński2Mieczysław Wodecki3Institute of Computer Engineering, Control and Robotics, Wrocław University of Technology, Janiszewskiego 11-17, 50-372 Wrocław, PolandInstitute of Construction, Wrocław University of Technology, Wyb. Wyspianskiego 27, 50-370 Wrocław, PolandInstitute of Computer Engineering, Control and Robotics, Wrocław University of Technology, Janiszewskiego 11-17, 50-372 Wrocław, PolandInstitute of Computer Science, University of Wrocław, Joliot-Curie 15, 50-383 Wrocław, PolandThe paper concerns the problem of roadworks scheduling executed in the flow-shop system. Works may be performed parallelly with the acceleration (overlaps) of construction project, i.e. the following work on the assembly line can begin before the completion of the predecessor work. Taking into account the acceleration enables accurate modeling of complex real construction processes. The above fact can greatly shorten the time of realization of construction process which has a direct impact on reducing costs. The considered issue belongs to the class of NP-hard problems. We introduce the new: mathematical model, specific properties as an acceleration tools, as well as two new optimization algorithms for the problem considered: construction and tabu search. The execution of algorithms was illustrated on the example of a case study concerning the construction of roads. They were also verified on the examples taken from the literature and on already completed construction processes. The obtained results are fully satisfactory. The assigned execution times are close to optimal. The presented methods allow its practitioners (both the planners and the managers) to include in the model the acceleration of the works and the design of a much more efficient construction scheduling. The presented new scheduling method leads to a more competitive environment for contraction companies.http://journals.vgtu.lt/index.php/JCEM/article/view/3159schedulingroad buildingflow shopoverlapstabu search
spellingShingle Wojciech Bożejko
Zdzisław Hejducki
Mariusz Uchroński
Mieczysław Wodecki
Solving resource-constrained construction scheduling problems with overlaps by metaheuristic
Journal of Civil Engineering and Management
scheduling
road building
flow shop
overlaps
tabu search
title Solving resource-constrained construction scheduling problems with overlaps by metaheuristic
title_full Solving resource-constrained construction scheduling problems with overlaps by metaheuristic
title_fullStr Solving resource-constrained construction scheduling problems with overlaps by metaheuristic
title_full_unstemmed Solving resource-constrained construction scheduling problems with overlaps by metaheuristic
title_short Solving resource-constrained construction scheduling problems with overlaps by metaheuristic
title_sort solving resource constrained construction scheduling problems with overlaps by metaheuristic
topic scheduling
road building
flow shop
overlaps
tabu search
url http://journals.vgtu.lt/index.php/JCEM/article/view/3159
work_keys_str_mv AT wojciechbozejko solvingresourceconstrainedconstructionschedulingproblemswithoverlapsbymetaheuristic
AT zdzisławhejducki solvingresourceconstrainedconstructionschedulingproblemswithoverlapsbymetaheuristic
AT mariuszuchronski solvingresourceconstrainedconstructionschedulingproblemswithoverlapsbymetaheuristic
AT mieczysławwodecki solvingresourceconstrainedconstructionschedulingproblemswithoverlapsbymetaheuristic