Network Planning Method in Optimizing Vessel Utilization – Laytime Calculation
The network planning method was chosen as a possible solution to management of optimizing vessel utilization. In addition to graphical presentation and project monitoring, this method allowed obtaining sufficient quantity of relevant information necessary to manage its realization. It was illustrate...
Main Authors: | , , |
---|---|
Format: | Article |
Language: | English |
Published: |
University of Dubrovnik
2018-01-01
|
Series: | Naše More (Dubrovnik) |
Subjects: | |
Online Access: | https://hrcak.srce.hr/file/302733 |
_version_ | 1797207640827232256 |
---|---|
author | Irena Mašće Romaldo Singolo Ino Jurišić |
author_facet | Irena Mašće Romaldo Singolo Ino Jurišić |
author_sort | Irena Mašće |
collection | DOAJ |
description | The network planning method was chosen as a possible solution to management of optimizing vessel utilization. In addition to graphical presentation and project monitoring, this method allowed obtaining sufficient quantity of relevant information necessary to manage its realization. It was illustrated with a hypothetical example of applying the network planning method in optimization of transhipment of containers in terms of time only, although the full contribution of network planning would be possible in the case of optimization of multimodal containership transport. |
first_indexed | 2024-04-24T09:26:08Z |
format | Article |
id | doaj.art-d176e39fcae64955bd2d4ee92a66daec |
institution | Directory Open Access Journal |
issn | 0469-6255 1848-6320 |
language | English |
last_indexed | 2024-04-24T09:26:08Z |
publishDate | 2018-01-01 |
publisher | University of Dubrovnik |
record_format | Article |
series | Naše More (Dubrovnik) |
spelling | doaj.art-d176e39fcae64955bd2d4ee92a66daec2024-04-15T15:00:59ZengUniversity of DubrovnikNaše More (Dubrovnik)0469-62551848-63202018-01-0165314615010.17818/NM/2018/3.3Network Planning Method in Optimizing Vessel Utilization – Laytime CalculationIrena Mašće0Romaldo Singolo1Ino Jurišić2University College of Inspection and Personnel Management in SplitUniversity of Split Faculty of Maritime Studies in SplitBrodograđevna industrija Split d.d. (Brodosplit)The network planning method was chosen as a possible solution to management of optimizing vessel utilization. In addition to graphical presentation and project monitoring, this method allowed obtaining sufficient quantity of relevant information necessary to manage its realization. It was illustrated with a hypothetical example of applying the network planning method in optimization of transhipment of containers in terms of time only, although the full contribution of network planning would be possible in the case of optimization of multimodal containership transport.https://hrcak.srce.hr/file/302733container transportnetwork planning methodmultimodal transport |
spellingShingle | Irena Mašće Romaldo Singolo Ino Jurišić Network Planning Method in Optimizing Vessel Utilization – Laytime Calculation Naše More (Dubrovnik) container transport network planning method multimodal transport |
title | Network Planning Method in Optimizing Vessel Utilization – Laytime Calculation |
title_full | Network Planning Method in Optimizing Vessel Utilization – Laytime Calculation |
title_fullStr | Network Planning Method in Optimizing Vessel Utilization – Laytime Calculation |
title_full_unstemmed | Network Planning Method in Optimizing Vessel Utilization – Laytime Calculation |
title_short | Network Planning Method in Optimizing Vessel Utilization – Laytime Calculation |
title_sort | network planning method in optimizing vessel utilization laytime calculation |
topic | container transport network planning method multimodal transport |
url | https://hrcak.srce.hr/file/302733 |
work_keys_str_mv | AT irenamasce networkplanningmethodinoptimizingvesselutilizationlaytimecalculation AT romaldosingolo networkplanningmethodinoptimizingvesselutilizationlaytimecalculation AT inojurisic networkplanningmethodinoptimizingvesselutilizationlaytimecalculation |