Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, Nigeria

Procurement method over time has proven to have significant influence on the successful delivery of construction projects. Making the right decision in the selection of a procurement option to adopt is therefore crucial if a project is to succeed. This study therefore assessed the cost and time perf...

Full description

Bibliographic Details
Main Authors: Aghimien Douglas Omoregie, Osanyinro Olufemi, Adegbembo Taiwo Fadeke
Format: Article
Language:English
Published: Sciendo 2017-12-01
Series:Organization, Technology and Management in Construction: An International Journal
Subjects:
Online Access:https://doi.org/10.1515/otmcj-2016-0022
_version_ 1797861996410961920
author Aghimien Douglas Omoregie
Osanyinro Olufemi
Adegbembo Taiwo Fadeke
author_facet Aghimien Douglas Omoregie
Osanyinro Olufemi
Adegbembo Taiwo Fadeke
author_sort Aghimien Douglas Omoregie
collection DOAJ
description Procurement method over time has proven to have significant influence on the successful delivery of construction projects. Making the right decision in the selection of a procurement option to adopt is therefore crucial if a project is to succeed. This study therefore assessed the cost and time performance of selected public building projects procured using traditional, direct labour and management procurement options in Ondo State, Nigeria. A pro forma was used to gather cost and time data from government procuring entities in the state. In addition, a structured questionnaire was used to obtain information from construction professionals in these procuring entities, in order to ascertain the factors influencing the choice of procurement options adopted. The cost and time data gathered were analyzed using percentages and the paired-samples t-test, while those gathered on the factors influencing the choice of procurement options were analyzed using mean item scores and analysis of variance (ANOVA). The results revealed that although there is no significant difference between the initial and final costs of the assessed projects, some measure of cost overrun still exists. In addition, a considerable amount of time overrun was experienced on projects executed using the three different procurement options. The most significant factors influencing the choice of a procurement option are price competition, speed, time certainty and complexity of the project. It is believed that the findings of this study will provide public procuring entities with insight on the cost and time capability of these procurement methods and aid them in selecting the procurement option that will help in delivering public building projects within the budget and on schedule.
first_indexed 2024-04-09T22:12:12Z
format Article
id doaj.art-d3d9538f7562482d9c731db29cb590c4
institution Directory Open Access Journal
issn 1847-6228
language English
last_indexed 2024-04-09T22:12:12Z
publishDate 2017-12-01
publisher Sciendo
record_format Article
series Organization, Technology and Management in Construction: An International Journal
spelling doaj.art-d3d9538f7562482d9c731db29cb590c42023-03-23T07:45:45ZengSciendoOrganization, Technology and Management in Construction: An International Journal1847-62282017-12-01911593160310.1515/otmcj-2016-0022otmcj-2016-0022Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, NigeriaAghimien Douglas Omoregie0Osanyinro Olufemi1Adegbembo Taiwo Fadeke2Federal University of Technology Akure Ondo State, NIGERIAB.Tech., Murty International Limited, Suite 308, Midel Centre, Plot 14, Off Oladipo Diya way, Sector Centre D, Gudu, Abuja, NigeriaM.Tech., Department of Quantity Surveying, Federal University of Technology, Akure, P.M.B. 704, Ondo State, NigeriaProcurement method over time has proven to have significant influence on the successful delivery of construction projects. Making the right decision in the selection of a procurement option to adopt is therefore crucial if a project is to succeed. This study therefore assessed the cost and time performance of selected public building projects procured using traditional, direct labour and management procurement options in Ondo State, Nigeria. A pro forma was used to gather cost and time data from government procuring entities in the state. In addition, a structured questionnaire was used to obtain information from construction professionals in these procuring entities, in order to ascertain the factors influencing the choice of procurement options adopted. The cost and time data gathered were analyzed using percentages and the paired-samples t-test, while those gathered on the factors influencing the choice of procurement options were analyzed using mean item scores and analysis of variance (ANOVA). The results revealed that although there is no significant difference between the initial and final costs of the assessed projects, some measure of cost overrun still exists. In addition, a considerable amount of time overrun was experienced on projects executed using the three different procurement options. The most significant factors influencing the choice of a procurement option are price competition, speed, time certainty and complexity of the project. It is believed that the findings of this study will provide public procuring entities with insight on the cost and time capability of these procurement methods and aid them in selecting the procurement option that will help in delivering public building projects within the budget and on schedule.https://doi.org/10.1515/otmcj-2016-0022costdirect labourmanagement procurementproject successpublic building projectstimetraditional procurement
spellingShingle Aghimien Douglas Omoregie
Osanyinro Olufemi
Adegbembo Taiwo Fadeke
Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, Nigeria
Organization, Technology and Management in Construction: An International Journal
cost
direct labour
management procurement
project success
public building projects
time
traditional procurement
title Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, Nigeria
title_full Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, Nigeria
title_fullStr Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, Nigeria
title_full_unstemmed Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, Nigeria
title_short Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, Nigeria
title_sort cost and time performance of traditional direct labour and management procured public projects in ondo state nigeria
topic cost
direct labour
management procurement
project success
public building projects
time
traditional procurement
url https://doi.org/10.1515/otmcj-2016-0022
work_keys_str_mv AT aghimiendouglasomoregie costandtimeperformanceoftraditionaldirectlabourandmanagementprocuredpublicprojectsinondostatenigeria
AT osanyinroolufemi costandtimeperformanceoftraditionaldirectlabourandmanagementprocuredpublicprojectsinondostatenigeria
AT adegbembotaiwofadeke costandtimeperformanceoftraditionaldirectlabourandmanagementprocuredpublicprojectsinondostatenigeria