Labor demand as a key factor in building process planning

Man or machine hours needed by various resources to complete construction works are the basis for work estimation and scheduling. In particular, they enable the planner to estimate labor costs or time needed to complete the task, review the resource of workload and availability of resources assigned...

Full description

Bibliographic Details
Main Author: Roman Marcinkowski
Format: Article
Language:English
Published: Lublin University of Technology 2013-03-01
Series:Budownictwo i Architektura
Subjects:
Online Access:https://ph.pollub.pl/index.php/bia/article/view/2163
_version_ 1797286916514643968
author Roman Marcinkowski
author_facet Roman Marcinkowski
author_sort Roman Marcinkowski
collection DOAJ
description Man or machine hours needed by various resources to complete construction works are the basis for work estimation and scheduling. In particular, they enable the planner to estimate labor costs or time needed to complete the task, review the resource of workload and availability of resources assigned to particular task, check the possibility of sharing resources across various tasks and determine other rates and factors useful in works scheduling. The project schedule can be analyzed both without or with and in consideration of risk of the end date of the project being pushed out or going over budget on the project. Issues presented above are the subject of this paper. The methods of solving described problems consider the optimization of a loss that derives from partial utilization of assigned the resources.
first_indexed 2024-03-07T18:25:16Z
format Article
id doaj.art-dace1c07ad6d4144ae82979867c708ed
institution Directory Open Access Journal
issn 1899-0665
2544-3275
language English
last_indexed 2024-03-07T18:25:16Z
publishDate 2013-03-01
publisher Lublin University of Technology
record_format Article
series Budownictwo i Architektura
spelling doaj.art-dace1c07ad6d4144ae82979867c708ed2024-03-02T07:05:05ZengLublin University of TechnologyBudownictwo i Architektura1899-06652544-32752013-03-0112110.35784/bud-arch.2163Labor demand as a key factor in building process planningRoman Marcinkowski0Faculty of Civil Engineering, Mechanics and Petrochemistry, Warsaw University of TechnologyMan or machine hours needed by various resources to complete construction works are the basis for work estimation and scheduling. In particular, they enable the planner to estimate labor costs or time needed to complete the task, review the resource of workload and availability of resources assigned to particular task, check the possibility of sharing resources across various tasks and determine other rates and factors useful in works scheduling. The project schedule can be analyzed both without or with and in consideration of risk of the end date of the project being pushed out or going over budget on the project. Issues presented above are the subject of this paper. The methods of solving described problems consider the optimization of a loss that derives from partial utilization of assigned the resources.https://ph.pollub.pl/index.php/bia/article/view/2163building process planningtotal labor demandlabor productivitytime of building task performance
spellingShingle Roman Marcinkowski
Labor demand as a key factor in building process planning
Budownictwo i Architektura
building process planning
total labor demand
labor productivity
time of building task performance
title Labor demand as a key factor in building process planning
title_full Labor demand as a key factor in building process planning
title_fullStr Labor demand as a key factor in building process planning
title_full_unstemmed Labor demand as a key factor in building process planning
title_short Labor demand as a key factor in building process planning
title_sort labor demand as a key factor in building process planning
topic building process planning
total labor demand
labor productivity
time of building task performance
url https://ph.pollub.pl/index.php/bia/article/view/2163
work_keys_str_mv AT romanmarcinkowski labordemandasakeyfactorinbuildingprocessplanning