The Impact of the Learning and Forgetting Effect on the Cost of a Multi-Unit Construction Project with the Use of the Simulated Annealing Algorithm

Construction projects are often delayed. Their budgets are being exceeded. This is partly because construction project models rarely take human factors into account. The article focuses on the repetitive multi-unit projects that are often found in construction practices. They are an excellent exampl...

Full description

Bibliographic Details
Main Authors: Michał Podolski, Jerzy Rosłon, Bartłomiej Sroka
Format: Article
Language:English
Published: MDPI AG 2022-12-01
Series:Applied Sciences
Subjects:
Online Access:https://www.mdpi.com/2076-3417/12/24/12667
_version_ 1797461657999376384
author Michał Podolski
Jerzy Rosłon
Bartłomiej Sroka
author_facet Michał Podolski
Jerzy Rosłon
Bartłomiej Sroka
author_sort Michał Podolski
collection DOAJ
description Construction projects are often delayed. Their budgets are being exceeded. This is partly because construction project models rarely take human factors into account. The article focuses on the repetitive multi-unit projects that are often found in construction practices. They are an excellent example of construction works for which the optimization of certain processes can bring measurable financial benefits. In particular, the focus was on improving the key investment success indicator, the total cost of a project. This article presents the use of learning and forgetting phenomenon to improve construction schedules. The authors proposed an innovative model of the construction phase and optimized the schedule using a proprietary calculation algorithm using the simulated annealing phenomenon. The method was verified by a series of experiments and showcased by a case study. The results show that the presented methods can improve the construction planning process and better reflect the current construction conditions. The findings may impact residential, infrastructure, industrial, and commercial construction branches.
first_indexed 2024-03-09T17:22:34Z
format Article
id doaj.art-e3431e2eecad410a8bb2fd4a9622a7e0
institution Directory Open Access Journal
issn 2076-3417
language English
last_indexed 2024-03-09T17:22:34Z
publishDate 2022-12-01
publisher MDPI AG
record_format Article
series Applied Sciences
spelling doaj.art-e3431e2eecad410a8bb2fd4a9622a7e02023-11-24T13:02:41ZengMDPI AGApplied Sciences2076-34172022-12-0112241266710.3390/app122412667The Impact of the Learning and Forgetting Effect on the Cost of a Multi-Unit Construction Project with the Use of the Simulated Annealing AlgorithmMichał Podolski0Jerzy Rosłon1Bartłomiej Sroka2Faculty of Civil Engineering, Wrocław University of Science and Technology, 50-370 Wrocław, PolandFaculty of Civil Engineering, Warsaw University of Technology, Armii Ludowej 16, 00-637 Warszawa, PolandFaculty of Civil Engineering, Cracow University of Technology, 31-155 Kraków, PolandConstruction projects are often delayed. Their budgets are being exceeded. This is partly because construction project models rarely take human factors into account. The article focuses on the repetitive multi-unit projects that are often found in construction practices. They are an excellent example of construction works for which the optimization of certain processes can bring measurable financial benefits. In particular, the focus was on improving the key investment success indicator, the total cost of a project. This article presents the use of learning and forgetting phenomenon to improve construction schedules. The authors proposed an innovative model of the construction phase and optimized the schedule using a proprietary calculation algorithm using the simulated annealing phenomenon. The method was verified by a series of experiments and showcased by a case study. The results show that the presented methods can improve the construction planning process and better reflect the current construction conditions. The findings may impact residential, infrastructure, industrial, and commercial construction branches.https://www.mdpi.com/2076-3417/12/24/12667learning and forgettingconstructionoptimizationmulti-unit projectsimulated annealingschedule
spellingShingle Michał Podolski
Jerzy Rosłon
Bartłomiej Sroka
The Impact of the Learning and Forgetting Effect on the Cost of a Multi-Unit Construction Project with the Use of the Simulated Annealing Algorithm
Applied Sciences
learning and forgetting
construction
optimization
multi-unit project
simulated annealing
schedule
title The Impact of the Learning and Forgetting Effect on the Cost of a Multi-Unit Construction Project with the Use of the Simulated Annealing Algorithm
title_full The Impact of the Learning and Forgetting Effect on the Cost of a Multi-Unit Construction Project with the Use of the Simulated Annealing Algorithm
title_fullStr The Impact of the Learning and Forgetting Effect on the Cost of a Multi-Unit Construction Project with the Use of the Simulated Annealing Algorithm
title_full_unstemmed The Impact of the Learning and Forgetting Effect on the Cost of a Multi-Unit Construction Project with the Use of the Simulated Annealing Algorithm
title_short The Impact of the Learning and Forgetting Effect on the Cost of a Multi-Unit Construction Project with the Use of the Simulated Annealing Algorithm
title_sort impact of the learning and forgetting effect on the cost of a multi unit construction project with the use of the simulated annealing algorithm
topic learning and forgetting
construction
optimization
multi-unit project
simulated annealing
schedule
url https://www.mdpi.com/2076-3417/12/24/12667
work_keys_str_mv AT michałpodolski theimpactofthelearningandforgettingeffectonthecostofamultiunitconstructionprojectwiththeuseofthesimulatedannealingalgorithm
AT jerzyrosłon theimpactofthelearningandforgettingeffectonthecostofamultiunitconstructionprojectwiththeuseofthesimulatedannealingalgorithm
AT bartłomiejsroka theimpactofthelearningandforgettingeffectonthecostofamultiunitconstructionprojectwiththeuseofthesimulatedannealingalgorithm
AT michałpodolski impactofthelearningandforgettingeffectonthecostofamultiunitconstructionprojectwiththeuseofthesimulatedannealingalgorithm
AT jerzyrosłon impactofthelearningandforgettingeffectonthecostofamultiunitconstructionprojectwiththeuseofthesimulatedannealingalgorithm
AT bartłomiejsroka impactofthelearningandforgettingeffectonthecostofamultiunitconstructionprojectwiththeuseofthesimulatedannealingalgorithm