Operation method of allowing variation interval of downstream water level in the middle route of South-to-North Water Diversion Project
To realize demand-oriented operations in the middle route of South-to-North Water Diversion Project, this paper proposed a pool operation method that a variation interval of water level at the upstream of the check gate is allowed. In this method, water users’ demand for flow changes can be satisfie...
Main Authors: | , , , |
---|---|
Format: | Article |
Language: | English |
Published: |
EDP Sciences
2018-01-01
|
Series: | MATEC Web of Conferences |
Online Access: | https://doi.org/10.1051/matecconf/201824601039 |
_version_ | 1819179012801429504 |
---|---|
author | Wu Yongyan Huang Huiyong Li Qi Yan Yibo |
author_facet | Wu Yongyan Huang Huiyong Li Qi Yan Yibo |
author_sort | Wu Yongyan |
collection | DOAJ |
description | To realize demand-oriented operations in the middle route of South-to-North Water Diversion Project, this paper proposed a pool operation method that a variation interval of water level at the upstream of the check gate is allowed. In this method, water users’ demand for flow changes can be satisfied as much as possible. Accordingly, downstream water depth is kept to fluctuate within a certain range, which is determined considering the canal safety, the operation frequency of check gates and the pool delay. The method is tested using the self-developed simulation platform for the middle route of South-to-North Water Diversion Project, which is established based on the Saint-Venant equations and programmed with the language Fortran. Results show that the flow changes demanded by water users, either increase or decrease, can be achieved effectively, while the water level variations can meet the restrictions for canal operation safety, and the frequency of gate adjustment is practically acceptable as well. Therefore, the operation method of allowing variation interval of downstream water level is suitable in the middle route of South-to-North Water Diversion Project at the current stage. |
first_indexed | 2024-12-22T21:51:41Z |
format | Article |
id | doaj.art-f5a645753f004f70988332dbbaadc448 |
institution | Directory Open Access Journal |
issn | 2261-236X |
language | English |
last_indexed | 2024-12-22T21:51:41Z |
publishDate | 2018-01-01 |
publisher | EDP Sciences |
record_format | Article |
series | MATEC Web of Conferences |
spelling | doaj.art-f5a645753f004f70988332dbbaadc4482022-12-21T18:11:21ZengEDP SciencesMATEC Web of Conferences2261-236X2018-01-012460103910.1051/matecconf/201824601039matecconf_iswso2018_01039Operation method of allowing variation interval of downstream water level in the middle route of South-to-North Water Diversion ProjectWu Yongyan0Huang Huiyong1Li Qi2Yan Yibo3Changjiang Institute of Survey, Planning, Design and Research, Planning departmentChangjiang Institute of Survey, Planning, Design and Research, Planning departmentChangjiang Institute of Survey, Planning, Design and Research, Planning departmentChangjiang Institute of Survey, Planning, Design and Research, Planning departmentTo realize demand-oriented operations in the middle route of South-to-North Water Diversion Project, this paper proposed a pool operation method that a variation interval of water level at the upstream of the check gate is allowed. In this method, water users’ demand for flow changes can be satisfied as much as possible. Accordingly, downstream water depth is kept to fluctuate within a certain range, which is determined considering the canal safety, the operation frequency of check gates and the pool delay. The method is tested using the self-developed simulation platform for the middle route of South-to-North Water Diversion Project, which is established based on the Saint-Venant equations and programmed with the language Fortran. Results show that the flow changes demanded by water users, either increase or decrease, can be achieved effectively, while the water level variations can meet the restrictions for canal operation safety, and the frequency of gate adjustment is practically acceptable as well. Therefore, the operation method of allowing variation interval of downstream water level is suitable in the middle route of South-to-North Water Diversion Project at the current stage.https://doi.org/10.1051/matecconf/201824601039 |
spellingShingle | Wu Yongyan Huang Huiyong Li Qi Yan Yibo Operation method of allowing variation interval of downstream water level in the middle route of South-to-North Water Diversion Project MATEC Web of Conferences |
title | Operation method of allowing variation interval of downstream water level in the middle route of South-to-North Water Diversion Project |
title_full | Operation method of allowing variation interval of downstream water level in the middle route of South-to-North Water Diversion Project |
title_fullStr | Operation method of allowing variation interval of downstream water level in the middle route of South-to-North Water Diversion Project |
title_full_unstemmed | Operation method of allowing variation interval of downstream water level in the middle route of South-to-North Water Diversion Project |
title_short | Operation method of allowing variation interval of downstream water level in the middle route of South-to-North Water Diversion Project |
title_sort | operation method of allowing variation interval of downstream water level in the middle route of south to north water diversion project |
url | https://doi.org/10.1051/matecconf/201824601039 |
work_keys_str_mv | AT wuyongyan operationmethodofallowingvariationintervalofdownstreamwaterlevelinthemiddlerouteofsouthtonorthwaterdiversionproject AT huanghuiyong operationmethodofallowingvariationintervalofdownstreamwaterlevelinthemiddlerouteofsouthtonorthwaterdiversionproject AT liqi operationmethodofallowingvariationintervalofdownstreamwaterlevelinthemiddlerouteofsouthtonorthwaterdiversionproject AT yanyibo operationmethodofallowingvariationintervalofdownstreamwaterlevelinthemiddlerouteofsouthtonorthwaterdiversionproject |