Causes of delay in residential construction projects in Cambodia

Construction industry is one of the significant contributors to the economic growth and development of Cambodia. Two major challenges are limiting the performance of the construction industry in Cambodia, which are poor cost and schedule performance of the construction projects. Therefore, the aim o...

Full description

Bibliographic Details
Main Authors: Serdar Durdyev, Maksat Omarov, Syuhaida Ismail
Format: Article
Language:English
Published: Taylor & Francis Group 2017-01-01
Series:Cogent Engineering
Subjects:
Online Access:http://dx.doi.org/10.1080/23311916.2017.1291117
_version_ 1797713991912390656
author Serdar Durdyev
Maksat Omarov
Syuhaida Ismail
author_facet Serdar Durdyev
Maksat Omarov
Syuhaida Ismail
author_sort Serdar Durdyev
collection DOAJ
description Construction industry is one of the significant contributors to the economic growth and development of Cambodia. Two major challenges are limiting the performance of the construction industry in Cambodia, which are poor cost and schedule performance of the construction projects. Therefore, the aim of this study is to fill an important knowledge gap by identifying the various attributes for construction project delay, using the residential building projects as a starting point. Feedback from a survey administered to the contractors and consultants was analysed using Relative Importance Index (RII). Results showed that shortage of materials on site; unrealistic project scheduling; late delivery of material; shortage of skilled labour; complexity of project; labour absenteeism; late payment by the owner for the completed work; poor site management; delay by subcontractor; accidents due to poor site safety are ranked by the contractors and consultants as the main causes of project delays in Cambodia. Construction frontline players are recommended to put their efforts on the identified key factors in relation to their magnitudes of influence. By doing so, the causes of project delays in the Cambodia’s construction and real estate sector could be significantly reduced or controlled, which will ultimately lead to the on time project completion.
first_indexed 2024-03-12T07:45:23Z
format Article
id doaj.art-f5c2e815dd1840b09d7a61501a0b5d5c
institution Directory Open Access Journal
issn 2331-1916
language English
last_indexed 2024-03-12T07:45:23Z
publishDate 2017-01-01
publisher Taylor & Francis Group
record_format Article
series Cogent Engineering
spelling doaj.art-f5c2e815dd1840b09d7a61501a0b5d5c2023-09-02T21:04:38ZengTaylor & Francis GroupCogent Engineering2331-19162017-01-014110.1080/23311916.2017.12911171291117Causes of delay in residential construction projects in CambodiaSerdar Durdyev0Maksat Omarov1Syuhaida Ismail2Zaman UniversityUTM Razak School of Engineering and Advanced TechnologyUTM Razak School of Engineering and Advanced TechnologyConstruction industry is one of the significant contributors to the economic growth and development of Cambodia. Two major challenges are limiting the performance of the construction industry in Cambodia, which are poor cost and schedule performance of the construction projects. Therefore, the aim of this study is to fill an important knowledge gap by identifying the various attributes for construction project delay, using the residential building projects as a starting point. Feedback from a survey administered to the contractors and consultants was analysed using Relative Importance Index (RII). Results showed that shortage of materials on site; unrealistic project scheduling; late delivery of material; shortage of skilled labour; complexity of project; labour absenteeism; late payment by the owner for the completed work; poor site management; delay by subcontractor; accidents due to poor site safety are ranked by the contractors and consultants as the main causes of project delays in Cambodia. Construction frontline players are recommended to put their efforts on the identified key factors in relation to their magnitudes of influence. By doing so, the causes of project delays in the Cambodia’s construction and real estate sector could be significantly reduced or controlled, which will ultimately lead to the on time project completion.http://dx.doi.org/10.1080/23311916.2017.1291117project delaysconstructioncambodiaresidential projects
spellingShingle Serdar Durdyev
Maksat Omarov
Syuhaida Ismail
Causes of delay in residential construction projects in Cambodia
Cogent Engineering
project delays
construction
cambodia
residential projects
title Causes of delay in residential construction projects in Cambodia
title_full Causes of delay in residential construction projects in Cambodia
title_fullStr Causes of delay in residential construction projects in Cambodia
title_full_unstemmed Causes of delay in residential construction projects in Cambodia
title_short Causes of delay in residential construction projects in Cambodia
title_sort causes of delay in residential construction projects in cambodia
topic project delays
construction
cambodia
residential projects
url http://dx.doi.org/10.1080/23311916.2017.1291117
work_keys_str_mv AT serdardurdyev causesofdelayinresidentialconstructionprojectsincambodia
AT maksatomarov causesofdelayinresidentialconstructionprojectsincambodia
AT syuhaidaismail causesofdelayinresidentialconstructionprojectsincambodia