Comparing the Costs of Intermittent and Dispatchable Electricity Generating Technologies

Economic evaluations of alternative electric generating technologies typically rely on comparisons between their expected life-cycle production costs per unit of electricity supplied. The standard life-cycle cost metric utilized is the “levelized cost” per MWh supplied. This paper demonstrates that...

Full description

Bibliographic Details
Main Author: Joskow, Paul L.
Format: Working Paper
Language:en_US
Published: MIT Center for Energy and Environmental Policy Research 2010
Online Access:http://hdl.handle.net/1721.1/59468
_version_ 1826189939311640576
author Joskow, Paul L.
author_facet Joskow, Paul L.
author_sort Joskow, Paul L.
collection MIT
description Economic evaluations of alternative electric generating technologies typically rely on comparisons between their expected life-cycle production costs per unit of electricity supplied. The standard life-cycle cost metric utilized is the “levelized cost” per MWh supplied. This paper demonstrates that this metric is inappropriate for comparing intermittent generating technologies like wind and solar with dispatchable generating technologies like nuclear, gas combined cycle, and coal. Levelized cost comparisons are a misleading metric for comparing intermittent and dispatchable generating technologies because they fail to take into account differences in the production profiles of intermittent and dispatchable generating technologies and the associated large variations in the market value of the electricity they supply. Levelized cost comparisons overvalue intermittent generating technologies compared to dispatchable base load generating technologies. They also overvalue wind generating technologies compared to solar generating technologies. Integrating differences in production profiles, the associated variations in the market value of the electricity supplied, and life-cycle costs associated with different generating technologies is necessary to provide meaningful comparisons between them. This market-based framework also has implications for the appropriate design of procurement auctions created to implement renewable energy procurement mandates, the efficient structure of production tax credits for renewable energy, and the evaluation of the additional costs of integrating intermittent generation into electric power networks.
first_indexed 2024-09-23T08:31:10Z
format Working Paper
id mit-1721.1/59468
institution Massachusetts Institute of Technology
language en_US
last_indexed 2024-09-23T08:31:10Z
publishDate 2010
publisher MIT Center for Energy and Environmental Policy Research
record_format dspace
spelling mit-1721.1/594682019-04-09T18:22:21Z Comparing the Costs of Intermittent and Dispatchable Electricity Generating Technologies Joskow, Paul L. Economic evaluations of alternative electric generating technologies typically rely on comparisons between their expected life-cycle production costs per unit of electricity supplied. The standard life-cycle cost metric utilized is the “levelized cost” per MWh supplied. This paper demonstrates that this metric is inappropriate for comparing intermittent generating technologies like wind and solar with dispatchable generating technologies like nuclear, gas combined cycle, and coal. Levelized cost comparisons are a misleading metric for comparing intermittent and dispatchable generating technologies because they fail to take into account differences in the production profiles of intermittent and dispatchable generating technologies and the associated large variations in the market value of the electricity they supply. Levelized cost comparisons overvalue intermittent generating technologies compared to dispatchable base load generating technologies. They also overvalue wind generating technologies compared to solar generating technologies. Integrating differences in production profiles, the associated variations in the market value of the electricity supplied, and life-cycle costs associated with different generating technologies is necessary to provide meaningful comparisons between them. This market-based framework also has implications for the appropriate design of procurement auctions created to implement renewable energy procurement mandates, the efficient structure of production tax credits for renewable energy, and the evaluation of the additional costs of integrating intermittent generation into electric power networks. - Massachusetts Institute of Technology. Center for Energy and Environmental Policy Research. 2010-10-22T14:40:19Z 2010-10-22T14:40:19Z 2010-09 Working Paper 2010-013 http://hdl.handle.net/1721.1/59468 en_US MIT-CEEPR (Series);2010-013 application/pdf MIT Center for Energy and Environmental Policy Research
spellingShingle Joskow, Paul L.
Comparing the Costs of Intermittent and Dispatchable Electricity Generating Technologies
title Comparing the Costs of Intermittent and Dispatchable Electricity Generating Technologies
title_full Comparing the Costs of Intermittent and Dispatchable Electricity Generating Technologies
title_fullStr Comparing the Costs of Intermittent and Dispatchable Electricity Generating Technologies
title_full_unstemmed Comparing the Costs of Intermittent and Dispatchable Electricity Generating Technologies
title_short Comparing the Costs of Intermittent and Dispatchable Electricity Generating Technologies
title_sort comparing the costs of intermittent and dispatchable electricity generating technologies
url http://hdl.handle.net/1721.1/59468
work_keys_str_mv AT joskowpaull comparingthecostsofintermittentanddispatchableelectricitygeneratingtechnologies