Summary: | Jogja Science Park is built with central government and region investment
as a mean to brace city term Yogyakarta as education city, influence economics
Yogyakarta and on a long term supposed can increase region original income
(PAD) city Yogyakarta. Investment aim reached when does Jogja Science Park�s
asset condition can awake well. For that need asset maintenance management both
for not only based on intuition, but as according to real situation. This research�s
goals aim analyzes factors have Jogja Science Park�s asset maintenance
management, then determine priority in Jogja Science Park�s asset maintenance
management.
This research uses mixed research methods that use qualitative and
quantitative data. Jogja Science Park�s asset in this research is divided in two
groups that are building, utilitas and park asset with boaster device asset criterias
with alternatives identified with carry out Focus Group Discussion (FGD) towards
entrant genuinely realize Jogja Science Park�s asset maintenance management. To
each criteria and alternatives then done weighting with method Analytic Hierarchy
Process (AHP) based on filler questionnaire that distributed to respondents in
concerned in Jogja Science Park�s asset maintenance management.
Found eleven factors have building, utility and park asset maintenance and
six factors have boaster device asset maintenance with result weighted with
produced sequence maintenance kind alternative priority for building, utility and
park asset routine maintenance with weight 0,299, corrective maintenance�s 0,254,
periodic maintenance�s 0,249, with predictive maintenance 0,198. Maintenance
kind alternative priority for boaster device asset routine maintenance with weight
0,302, corrective maintenance�s 0,289, periodic maintenance�s 0,238, with
predictive maintenance 0,171. AHP�s result besides tested the consistency also
pass sensitivity analysis and compared with TOPSIS and VIKOR analysis.
|