ANALISIS CAPACITY CONSTRAINED WORKER (CCW) DENGAN PENDEKATAN WAKTU BAKU DAN DENYUT JANTUNG PEKERJA (STUDI PADA : INDUSTRI TEMPE �MUCHLAR�KASIHAN BANTUL YOGYAKARTA)
One of the factors of production that plays an important role in determining the efficiency and effectiveness of production is worker. worker can also be an obstacle for an industry which, if not identified could disturb the goal. One of the concepts that can be used to identify any constraints exis...
Main Authors: | , |
---|---|
Format: | Thesis |
Published: |
[Yogyakarta] : Universitas Gadjah Mada
2013
|
Subjects: |
Summary: | One of the factors of production that plays an important role in
determining the efficiency and effectiveness of production is worker. worker can
also be an obstacle for an industry which, if not identified could disturb the goal.
One of the concepts that can be used to identify any constraints existing work in
an industry is the Theory of Constraints (TOC). TOC recognizes that the
performance of each company is limited by constraints. Tempe \"Muchlar\" is one
of the food industry that all the work is done manually so that the production
process is highly dependent on the capacity of the workforce. Problems arise
because the target tempe production of semi-finished for 3600 + kg is not reached.
This study aims to identify the worker happens Capacity constrained approach of
standard time and may determine the appropriate improvements to increase
capacity
This study was conducted to quantify and determine the factors that affect
the capacity of workers such as heart rate, standard time workers and the
environment. Of these data can be identified as a potential Capacity Constrained
worker indicated by the weakest workers. Subsequently obtained from the
standard time can be determined Capacity Constrained worker by comparing the
output targets
From the results of this study determined that the Capacity Constrained
worker is a peeling station. This is evidenced from the standard time of 5.63
seconds gained / kg which makes a production target of 3,600 kg in 5 hours is not
reached. With the improvements made to the lowering of the room temperature to
the normal high standard time workers can be increased to 5 sec / kg and
production targets can be achieved and increase revenue. And by applying
management buffer rediscovered not be constraint work stations
. |
---|