EVALUASI TERHADAP RENCANA PEMINDAHAN BEBAN DARI FEEDER KENTUNGAN 7 KE FEEDER GEJAYAN 19
Kentungan substation feeders have 12 pieces of 2 pieces each transformer capacity of 60 MVA . Transformer IV connected with feeders KTN - 7 to supply the area north jogja and Kalasan . Seen from the data disruption and expense data , feeders KTN - 7 is one of the feeders are often susceptible to int...
Main Authors: | , |
---|---|
Format: | Thesis |
Published: |
[Yogyakarta] : Universitas Gadjah Mada
2013
|
Subjects: |
_version_ | 1826047705166643200 |
---|---|
author | , FITRI RACHMANINGRUM , Ir. M. Isnaeni B.S. M.T. |
author_facet | , FITRI RACHMANINGRUM , Ir. M. Isnaeni B.S. M.T. |
author_sort | , FITRI RACHMANINGRUM |
collection | UGM |
description | Kentungan substation feeders have 12 pieces of 2 pieces each transformer
capacity of 60 MVA . Transformer IV connected with feeders KTN - 7 to supply
the area north jogja and Kalasan . Seen from the data disruption and expense
data , feeders KTN - 7 is one of the feeders are often susceptible to interference
and already exceeds the maximum capacity of the economic loading of a
conductor . Construction of Medium Voltage Air Channel network used by feeders
KTN - 7 using a 240mm2 AAAC wire has a minimum load limit of 150 A and
maximum economic loading of 300 A.
Quality of electricity service seen from the quality of the voltage supplied
to consumers and continuity of power supply to consumers. With these
considerations, the evaluation is done by dividing the load in the network Kalasan
area with a new feeder , the feeder GJN - 19 derived from Gejayan substation .
This feeder is an express feeder which will use cord MVTIC / NFA2XSEY - T
3x240+150 .
This evaluation will be based on the calculation of losses , voltage drop ,
as well as the calculation of the reliability index of the placement of the
intersection of the load displacement feeder KTN 7 to feeder GJN 19 . |
first_indexed | 2024-03-13T23:15:06Z |
format | Thesis |
id | oai:generic.eprints.org:126830 |
institution | Universiti Gadjah Mada |
last_indexed | 2024-03-13T23:15:06Z |
publishDate | 2013 |
publisher | [Yogyakarta] : Universitas Gadjah Mada |
record_format | dspace |
spelling | oai:generic.eprints.org:1268302016-03-04T08:36:09Z https://repository.ugm.ac.id/126830/ EVALUASI TERHADAP RENCANA PEMINDAHAN BEBAN DARI FEEDER KENTUNGAN 7 KE FEEDER GEJAYAN 19 , FITRI RACHMANINGRUM , Ir. M. Isnaeni B.S. M.T. ETD Kentungan substation feeders have 12 pieces of 2 pieces each transformer capacity of 60 MVA . Transformer IV connected with feeders KTN - 7 to supply the area north jogja and Kalasan . Seen from the data disruption and expense data , feeders KTN - 7 is one of the feeders are often susceptible to interference and already exceeds the maximum capacity of the economic loading of a conductor . Construction of Medium Voltage Air Channel network used by feeders KTN - 7 using a 240mm2 AAAC wire has a minimum load limit of 150 A and maximum economic loading of 300 A. Quality of electricity service seen from the quality of the voltage supplied to consumers and continuity of power supply to consumers. With these considerations, the evaluation is done by dividing the load in the network Kalasan area with a new feeder , the feeder GJN - 19 derived from Gejayan substation . This feeder is an express feeder which will use cord MVTIC / NFA2XSEY - T 3x240+150 . This evaluation will be based on the calculation of losses , voltage drop , as well as the calculation of the reliability index of the placement of the intersection of the load displacement feeder KTN 7 to feeder GJN 19 . [Yogyakarta] : Universitas Gadjah Mada 2013 Thesis NonPeerReviewed , FITRI RACHMANINGRUM and , Ir. M. Isnaeni B.S. M.T. (2013) EVALUASI TERHADAP RENCANA PEMINDAHAN BEBAN DARI FEEDER KENTUNGAN 7 KE FEEDER GEJAYAN 19. UNSPECIFIED thesis, UNSPECIFIED. http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=67064 |
spellingShingle | ETD , FITRI RACHMANINGRUM , Ir. M. Isnaeni B.S. M.T. EVALUASI TERHADAP RENCANA PEMINDAHAN BEBAN DARI FEEDER KENTUNGAN 7 KE FEEDER GEJAYAN 19 |
title | EVALUASI TERHADAP RENCANA PEMINDAHAN BEBAN DARI FEEDER KENTUNGAN 7 KE FEEDER GEJAYAN 19 |
title_full | EVALUASI TERHADAP RENCANA PEMINDAHAN BEBAN DARI FEEDER KENTUNGAN 7 KE FEEDER GEJAYAN 19 |
title_fullStr | EVALUASI TERHADAP RENCANA PEMINDAHAN BEBAN DARI FEEDER KENTUNGAN 7 KE FEEDER GEJAYAN 19 |
title_full_unstemmed | EVALUASI TERHADAP RENCANA PEMINDAHAN BEBAN DARI FEEDER KENTUNGAN 7 KE FEEDER GEJAYAN 19 |
title_short | EVALUASI TERHADAP RENCANA PEMINDAHAN BEBAN DARI FEEDER KENTUNGAN 7 KE FEEDER GEJAYAN 19 |
title_sort | evaluasi terhadap rencana pemindahan beban dari feeder kentungan 7 ke feeder gejayan 19 |
topic | ETD |
work_keys_str_mv | AT fitrirachmaningrum evaluasiterhadaprencanapemindahanbebandarifeederkentungan7kefeedergejayan19 AT irmisnaenibsmt evaluasiterhadaprencanapemindahanbebandarifeederkentungan7kefeedergejayan19 |