Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project

Delays in construction projects are a common phenomenon throughout the industry. This problem has many negative impacts on the time, cost, and sustainability of the projects. Many studies were conducted to identify the main causes of this delay in new construction projects in different regions but v...

Full description

Bibliographic Details
Main Authors: Al Khatib, Basem, Yap, Soon Poh, El-Shafie, Ahmed
Format: Article
Published: MDPI 2018
Subjects:
_version_ 1796961473156612096
author Al Khatib, Basem
Yap, Soon Poh
El-Shafie, Ahmed
author_facet Al Khatib, Basem
Yap, Soon Poh
El-Shafie, Ahmed
author_sort Al Khatib, Basem
collection UM
description Delays in construction projects are a common phenomenon throughout the industry. This problem has many negative impacts on the time, cost, and sustainability of the projects. Many studies were conducted to identify the main causes of this delay in new construction projects in different regions but very few studies have focused on finding an explanation for the causes of delay in major reconstruction projects that have great religious and cultural sustainability. This paper examines the factors that contributed to work delays in one of the most major reconstruction projects that took place recently in the Middle East, which is namely the Mataf Expansion Project in the city of Mecca, Saudi Arabia. Fourteen interviews were conducted with project managers, construction managers, and senior site engineers to identify the factors that they encountered and led to the delay in the reconstruction activities of this project. Some of the findings were consistent and similar to most other causes of delay that are associated with new construction projects. However, interestingly, this research has discovered the existence of other unavoidable factors that caused a delay and should be considered for any similar reconstruction projects. The results showed that these factors could be divided into two groups: the first one is related to the demolition phase (five factors) and the second group is related to construction works (nine factors). In addition, it has been observed that the building material during the reconstruction is considered one of the major delaying factors. Finally, these 14 delay factors should be carefully considered to assure the sustainability of the main object's function during the reconstruction activities.
first_indexed 2024-03-06T05:54:38Z
format Article
id um.eprints-21617
institution Universiti Malaya
last_indexed 2024-03-06T05:54:38Z
publishDate 2018
publisher MDPI
record_format dspace
spelling um.eprints-216172019-07-15T05:12:55Z http://eprints.um.edu.my/21617/ Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project Al Khatib, Basem Yap, Soon Poh El-Shafie, Ahmed TA Engineering (General). Civil engineering (General) Delays in construction projects are a common phenomenon throughout the industry. This problem has many negative impacts on the time, cost, and sustainability of the projects. Many studies were conducted to identify the main causes of this delay in new construction projects in different regions but very few studies have focused on finding an explanation for the causes of delay in major reconstruction projects that have great religious and cultural sustainability. This paper examines the factors that contributed to work delays in one of the most major reconstruction projects that took place recently in the Middle East, which is namely the Mataf Expansion Project in the city of Mecca, Saudi Arabia. Fourteen interviews were conducted with project managers, construction managers, and senior site engineers to identify the factors that they encountered and led to the delay in the reconstruction activities of this project. Some of the findings were consistent and similar to most other causes of delay that are associated with new construction projects. However, interestingly, this research has discovered the existence of other unavoidable factors that caused a delay and should be considered for any similar reconstruction projects. The results showed that these factors could be divided into two groups: the first one is related to the demolition phase (five factors) and the second group is related to construction works (nine factors). In addition, it has been observed that the building material during the reconstruction is considered one of the major delaying factors. Finally, these 14 delay factors should be carefully considered to assure the sustainability of the main object's function during the reconstruction activities. MDPI 2018 Article PeerReviewed Al Khatib, Basem and Yap, Soon Poh and El-Shafie, Ahmed (2018) Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project. Sustainability, 10 (12). p. 4772. ISSN 2071-1050, DOI https://doi.org/10.3390/su10124772 <https://doi.org/10.3390/su10124772>. https://doi.org/10.3390/su10124772 doi:10.3390/su10124772
spellingShingle TA Engineering (General). Civil engineering (General)
Al Khatib, Basem
Yap, Soon Poh
El-Shafie, Ahmed
Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project
title Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project
title_full Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project
title_fullStr Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project
title_full_unstemmed Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project
title_short Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project
title_sort delay factors in reconstruction projects a case study of mataf expansion project
topic TA Engineering (General). Civil engineering (General)
work_keys_str_mv AT alkhatibbasem delayfactorsinreconstructionprojectsacasestudyofmatafexpansionproject
AT yapsoonpoh delayfactorsinreconstructionprojectsacasestudyofmatafexpansionproject
AT elshafieahmed delayfactorsinreconstructionprojectsacasestudyofmatafexpansionproject