Study of factors influencing construction delays at rural area in Malaysia
Construction is one of an important industry which contributes to the economic growth in Malaysia. However, it has been revealed that 79.5 percent and 66.7 percent of the public and private projects were not completed within the time specified in the contracts out of 359 projects in Malaysia. Theref...
Main Authors: | , , , , , , , |
---|---|
Format: | Article |
Published: |
INSTITUTE OF PHYSICS PUBLISHING
2018
|
Subjects: |
_version_ | 1825710266609827840 |
---|---|
author | Ramli, M Z Malek, M A Hanipah, M. H. Lin, C L Mahamad Sukri, M F Zawawi, M H Zainal Abidin, M Z Mohamad Fuad, N F S |
author_facet | Ramli, M Z Malek, M A Hanipah, M. H. Lin, C L Mahamad Sukri, M F Zawawi, M H Zainal Abidin, M Z Mohamad Fuad, N F S |
author_sort | Ramli, M Z |
collection | UTHM |
description | Construction is one of an important industry which contributes to the economic growth in Malaysia. However, it has been revealed that 79.5 percent and 66.7 percent of the public and private projects were not completed within the time specified in the contracts out of 359 projects in Malaysia. Therefore, the purpose of this study is to investigate the delay factor caused project delay at rural area. A 5-points Likert scale questionnaire survey were answered by 111 respondents which having experience with rural construction project. The questionnaire data were analysed by using Relative Importance Index (RII). Five top factors were determined from this study based on their RII values which are improper construction method implemented by contractor, weather condition, difficulties in providing delivery to site, breakdown of site equipment, and poor qualification of contractor’s technical staffs. |
first_indexed | 2024-03-05T21:55:00Z |
format | Article |
id | uthm.eprints-6854 |
institution | Universiti Tun Hussein Onn Malaysia |
last_indexed | 2024-03-05T21:55:00Z |
publishDate | 2018 |
publisher | INSTITUTE OF PHYSICS PUBLISHING |
record_format | dspace |
spelling | uthm.eprints-68542022-04-04T04:20:30Z http://eprints.uthm.edu.my/6854/ Study of factors influencing construction delays at rural area in Malaysia Ramli, M Z Malek, M A Hanipah, M. H. Lin, C L Mahamad Sukri, M F Zawawi, M H Zainal Abidin, M Z Mohamad Fuad, N F S TH Building construction Construction is one of an important industry which contributes to the economic growth in Malaysia. However, it has been revealed that 79.5 percent and 66.7 percent of the public and private projects were not completed within the time specified in the contracts out of 359 projects in Malaysia. Therefore, the purpose of this study is to investigate the delay factor caused project delay at rural area. A 5-points Likert scale questionnaire survey were answered by 111 respondents which having experience with rural construction project. The questionnaire data were analysed by using Relative Importance Index (RII). Five top factors were determined from this study based on their RII values which are improper construction method implemented by contractor, weather condition, difficulties in providing delivery to site, breakdown of site equipment, and poor qualification of contractor’s technical staffs. INSTITUTE OF PHYSICS PUBLISHING 2018 Article PeerReviewed Ramli, M Z and Malek, M A and Hanipah, M. H. and Lin, C L and Mahamad Sukri, M F and Zawawi, M H and Zainal Abidin, M Z and Mohamad Fuad, N F S (2018) Study of factors influencing construction delays at rural area in Malaysia. International PostGraduate Conference on Applied Science & Physics. pp. 1-8. ISSN 1742-6588 https://doi.org/10.1088/1742-6596/1049/1/012017 |
spellingShingle | TH Building construction Ramli, M Z Malek, M A Hanipah, M. H. Lin, C L Mahamad Sukri, M F Zawawi, M H Zainal Abidin, M Z Mohamad Fuad, N F S Study of factors influencing construction delays at rural area in Malaysia |
title | Study of factors influencing construction delays at rural area in Malaysia |
title_full | Study of factors influencing construction delays at rural area in Malaysia |
title_fullStr | Study of factors influencing construction delays at rural area in Malaysia |
title_full_unstemmed | Study of factors influencing construction delays at rural area in Malaysia |
title_short | Study of factors influencing construction delays at rural area in Malaysia |
title_sort | study of factors influencing construction delays at rural area in malaysia |
topic | TH Building construction |
work_keys_str_mv | AT ramlimz studyoffactorsinfluencingconstructiondelaysatruralareainmalaysia AT malekma studyoffactorsinfluencingconstructiondelaysatruralareainmalaysia AT hanipahmh studyoffactorsinfluencingconstructiondelaysatruralareainmalaysia AT lincl studyoffactorsinfluencingconstructiondelaysatruralareainmalaysia AT mahamadsukrimf studyoffactorsinfluencingconstructiondelaysatruralareainmalaysia AT zawawimh studyoffactorsinfluencingconstructiondelaysatruralareainmalaysia AT zainalabidinmz studyoffactorsinfluencingconstructiondelaysatruralareainmalaysia AT mohamadfuadnfs studyoffactorsinfluencingconstructiondelaysatruralareainmalaysia |