Liquidated and ascertained damages (LAD) and requirements of mitigation
When a project is late in completion due to contractor’s fault, the employer is entitled to a contractual remedy by enforcing the Liquidated and Ascertained Damages (LAD) provisions. However, contractors often seek to challenge the enforceability of LAD by alleging that the employers suffer no los...
Main Author: | Yong, Mei Lee |
---|---|
Format: | Thesis |
Language: | English |
Published: |
2006
|
Subjects: | |
Online Access: | http://eprints.utm.my/2363/1/YongMeiLeeMFAB2006.pdf |
Similar Items
-
Liquidated and ascertained damage (LAD) and requirements of mitigation /
by: 280249 Yong, Mei Lee
Published: (2006) -
Liquidated and ascertained damage (LAD) and requirements of mitigation [compact disc] /
by: 280249 Yong, Mei Lee
Published: (2006) -
Notice condition precedent to claim liquidated ascertained damages (LAD) /
by: Nur Syaimasyaza Mansor, 1987-, et al.
Published: (2011) -
Notice condition precedent to claim liquidated ascertained damages (LAD) [electronic resource] /
by: Nur Syaimasyaza Mansor, 1987-
Published: (2011) -
Ascertaining government's vicarious liability: a review of Kerajaan Malaysia & Ors v Lay Kee Tee & Ors [2009] 1 MLJ 1
by: Ali Mohamed, Ashgar Ali
Published: (2009)