Pemakaian Temporary Tower untuk Optimalisasi Penyelesaian Rekonduktoring dan Penggantian Tower Saluran Udara Tegangan Tinggi (SUTT) 150 KV
The use of temporary towers is a solution to shorten the outage time. Temporary Tower is used as a tool in reconductoring work and tower replacement. The study by calculating the Budget Plan Cost (RAB) and schedule analysis using Microsoft Project Application to determine the comparative duration of...