Analysis and Treatment of Vibration Fault of a 1 050 MW Steam Turbine Generating Unit

During the capital construction commissioning of unit No.1 of a 2×1 050 MW coal-fired power plant, vibration of bearings No.5 and No.6 exceeded the set standard and become rather unstable, holding up the project. Through vibration test and analysis, it is found that: 1)there are dynamic and static c...