Time buffers in construction process scheduling

Potential applications of the CCS/BM method in the scheduling of continuous LSM (Linear Scheduling Model) construction activities are considered. The effect of time buffers – feeding buffers (FB) and project buffers (PB) – on total project realisation time (TT) is examined. Feeding buffers are found...

Full description

Bibliographic Details
Main Authors: Magdalena Rogalska, Zdzisław Hejducki
Format: Article
Language:English
Published: Vilnius Gediminas Technical University 2007-06-01
Series:Journal of Civil Engineering and Management
Subjects:
Online Access:https://journals.vgtu.lt/index.php/JCEM/article/view/7674