Cash Flow Optimization for Renewable Energy Construction Projects with a New Approach to Critical Chain Scheduling

This study concerns the use of the critical chain method to schedule the construction of renewable energy facilities. The critical chain method is recognized as a useful project management tool, transforming a stochastic problem of uncertainty in activity durations into a deterministic one. However,...