OPTIMALISASI WAKTU DAN BIAYA PELAKSANAAN PROYEK MENGGUNAKAN METODE LEAST COST ANALYSIS (Studi Kasus : Pembangunan Pasar Amlapura Barat)

Abstract: Construction projects can be completed successfully based on careful planning. However, in the implementation of the West Amlapura Market development project, it requires an additional 50 calendar days to complete the work where the project is delayed by 24.468% in the 20th week with the r...