Prediction and Performance of Deep Excavations for Courthouse Station, Boston

Construction of the Silverline Courthouse Station in South Boston involved 18-m-deep excavations at a site underlain by more than 24 m of normally and lightly overconsolidated Boston blue clay (BBC). The excavations were supported by 27-m-deep floating diaphragm wall panels and five levels of preloa...